Previous Topic: Managing ProjectsNext Topic: Scheduling (projects)


How to Set Up a CA Clarity PPM Project

A project is the most common work plan, and is typically derived from ideas, proposals, unapproved projects, your backlog, or service requests. You prioritize and approve projects based on a number of key factors, including the following items:

Projects are the core investment in the application. Understanding how to create projects enables you to properly manage them. Creating projects is the first step in the project management process.

The following diagram describes how a project manager sets up a CA Clarity PPM project.

how_to_set_up_a_cappm_project

To set up a CA Clarity PPM project, perform these steps:

  1. Review the prerequisites.
  2. Create the project:
  3. Define the project properties:
  4. Create the project team:
  5. Create the project tasks.
  6. Assign resources to the project tasks.

Note: This scenario does not include all of the terminology that is involved in setting up a CA Clarity PPM project. For more information, see the Project Management User Guide.

Review the Prerequisites

To complete all tasks in this scenario, consider the following information:

Initial Project Planning

Resources and roles

All resources who participate in the project are defined. All the roles in the project are defined.

Note: This scenario does not explain how to create a resource. For more information about creating a resource, see the Resource Management User Guide.

Departments

A department is created for the project.

Note: This scenario does not explain how to create a department. For more information about creating a department, see the Financial Management User Guide.

Access Rights

You need specific access rights to set up a project.

Note: For more information about access rights, see the Administration Guide or contact your system administrator.

Create the Project

As a project manager, you create the project to track the work plan for your investments. For example, you have a new development project that has been approved for the upcoming fiscal year.

To create the project, follow one of these methods:

Note: You can also create the project using XOG, by converting an idea to a project, using Open Workbench, and using Microsoft Project. This scenario does not explain these methods.

Create the Project from a Template

As a project manager, you can create the project from a template. Templates help enforce consistency and improve efficiency when creating projects.

You can create a project and save it as a template. Others can use this template to create a project.

When you create a project from a template, the following information is copied from the template to the new project:

Note: Start and finish dates, baseline information, and financial properties are not copied from templates to new projects. If hard-booked resources are defined in the project template, the resources are copied as soft-booked.

Follow these steps:

  1. Open Home, and from Portfolio Management, click Projects.
  2. Click New from Template.
  3. Filter to select a template and click Next.
  4. Complete the fields in the General section. The following fields require explanation:
    % Complete Calculation Method

    Specifies the method to calculate the % Complete value for the project and tasks.

    Values:

    • Manual. Use this method to enter the % Complete for the project, summary, and detail tasks manually. Also, select this calculation method if you are using CA Clarity PPM with Microsoft Project, or if you are using an external job to calculate % Complete. The % Complete field appears on the task properties page.
    • Duration. Use this method to track the % Complete based on the duration. The duration is a measure of the total span of active working time for a task: from the start date to the finish date of a task. The % Complete for summary tasks is automatically calculated based on the following formula:
      Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
      
    • Effort. Use this method to calculate the % Complete for summary and detail tasks, automatically, based on the work units that are completed by resource assignments. If you assign a nonlabor resource to a task, the effort and actuals for that resource are ignored in the calculation. The calculations are based on the following formulas.
      Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort
      Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
      

    Default: Manual

    Note: Set the % Complete Calculation Method at the beginning of your project and do not change this value.

    Assignment Pool

    Specifies the pool of resources that is allowed when assigning resources to tasks.

    Values:

    • Team Only. Allow only staff members.
    • Resource Pool. Allow team staff members and resources for whom you have access rights to book to a project. With this option, when you assign a resource to a task, the resource is also added as a team staff member.

    Default: Resource Pool

    Set Planned Cost Dates

    Specifies if the planned cost dates are synchronized with the investment dates. Selecting the option for a detailed financial plan does not affect the planned cost dates.

    Default: Selected

  5. Complete the fields in the Organizational Breakdown Structures section. This information defines the OBS to associate with the project for security, organizational, or reporting purposes.
  6. Complete the fields in the Copy Template Project Options section. The following fields require explanation:
    Scale Work By

    Defines the percentage by which the work estimate on each task is required to be increased or decreased for the new project. The scaling is relative to the template.

    Values: 0-100 (where zero means no change)

    Default: Zero

    Scale Budget By

    Defines the percentage (positive or negative) as the scaling factor for the dollar amounts defined in the project cost plans and benefit plans.

    Values: 0-100 (where zero means no change)

    Default: Zero

    Example: The template project from 1/1/2012 to 12/31/2012 allocates $10,000 for planned cost and $20,000 for planned benefit for the project duration. If a Scale Budget By value of 20 percent is defined, the plans copy over to the new project as follows. Assume that the project duration is same as the template project:

    • The planned cost shows $12,000 (scaled up by an extra 20 percent of the original value).
    • The planned benefit shows $24,000 (scaled up by an extra 20 percent of the original value).
    Convert resources to roles

    Specifies to replace the resources in the new project with the primary roles, or team roles of the named resources on the project template. If a named resource has no primary role or team role, the named resource is retained on the new project. This setting overrides the default project management setting on the settings page.

    For example, a cost plan uses a resource as a grouping attribute. When you select this check box, the cost plan from the template is copied. However, the resource values are not converted to roles. The resource value can be the only value that differentiates one line item detail row from another. In the absence of the value, duplicate detail rows can result in the cost plan.

    Default: Cleared

  7. Save your changes.

Create the Project Manually

As a project manager, you can create the project manually, if you do not want to use an existing template.

Follow these steps:

  1. Open Home, and from Portfolio Management, click Projects.
  2. Click New.
  3. Complete the fields in the General section. The following fields require explanation:
    % Complete Calculation Method

    Specifies the method to calculate the % Complete value for the project and tasks.

    Values:

    • Manual. Use this method to enter the % Complete for the project, summary, and detail tasks manually. Also, select this calculation method if you are using CA Clarity PPM with Microsoft Project, or if you are using an external job to calculate % Complete. The % Complete field appears on the task properties page.
    • Duration. Use this method to track the % Complete based on the duration. The duration is a measure of the total span of active working time for a task: from the start date to the finish date of a task. The % Complete for summary tasks is automatically calculated based on the following formula:
      Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
      
    • Effort. Use this method to calculate the % Complete for summary and detail tasks, automatically, based on the work units that are completed by resource assignments. If you assign a nonlabor resource to a task, the effort and actuals for that resource are ignored in the calculation. The calculations are based on the following formulas.
      Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort
      Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
      

    Default: Manual

    Note: Set the % Complete Calculation Method at the beginning of your project and do not change this value.

    Assignment Pool

    Specifies the pool of resources that is allowed when assigning resources to tasks.

    Values:

    • Team Only. Allow only staff members.
    • Resource Pool. Allow team staff members and resources for whom you have access rights to book to a project. With this option, when you assign a resource to a task, the resource is also added as a team staff member.

    Default: Resource Pool

    Set Planned Cost Dates

    Specifies if the planned cost dates are synchronized with the investment dates. Selecting the option for a detailed financial plan does not affect the planned cost dates.

    Default: Selected
  4. Complete the fields in the Organizational Breakdown Structures section. This information defines the OBS to associate with the project for security, organizational, or reporting purposes.
  5. Save your changes.

Define the Project Properties

After you create a project with the basic information, define the project properties. Project properties include the following:

To define the project properties, complete the following tasks:

Note: This scenario does not explain all of these tasks in detail. For more information about these tasks, see the Project Management User Guide.

Define the General Properties

Specifying the general properties of a project help identify it and define its characteristics.

Follow these steps:

  1. Open the project.
  2. Complete the fields in the General section. The following fields require explanation:
    Manager

    Specifies the resource who created the project. If necessary, you can update this field.

    Note: The list of participants that appear on the Team, Participant page also depends on the value that you select for the Administration, Project Management, Settings, Automatically Add Staff Members As Investment Participant option.

    • The Manager becomes the Collaboration Manager under the Participants list.
    • All the team members become participants.
    Page Layout

    Specifies the page layout to view project information. The available layouts are company-specific and depend on the values set by your CA Clarity PPM administrator. Layouts also depend on whether an add-in is installed. If other layouts are not available, the field is read-only.

    Default: Project Default Layout

    Risk

    Specifies the risk level of the project as defined by the severity levels you select for the predefined list of risk factors from the main risk page.

    Goal

    Specifies the purpose or business case for the project.

    Values: Cost Avoidance, Cost Reduction, Grow the Business, Infrastructure Improvement, and Maintain the Business

    Alignment

    Specifies the alignment with corporate objectives. Displays a stoplight that indicates the project alignment status.

    Values:

    • 66 - 100 (Green) = Aligned
    • 33 - 65 (Yellow) = Alignment at risk
    • 0 - 32 (Red) = Out of alignment
    Status

    Indicates the status of the investment.

    Values: Approved, Rejected, Unapproved

    Default: Unapproved

    Active

    Specifies if the investment is active. Activate the investment to enable the posting of transactions and to view the investment in capacity planning portlets.

    Default: Selected

    Program

    Specifies that you want to use a program to create projects.

    Default: Cleared

    Template

    Specifies that you want to use the project as a project template to create other projects.

    Default: Cleared

    Required

    Specifies to pin this investment when added to a portfolio. This field is used during scenario generation.

    Default: Cleared

Define the Scheduling Properties

You define scheduling properties for the following reasons:

Follow these steps:

  1. Open the project.
  2. Open the Properties menu, and from Properties, click Schedule.
  3. Complete the fields in the Schedule section. The following fields require explanation:
    As Of Date

    Defines the date to include data in time and budget estimates. This date is used in Earned Value Analysis (EVA) calculations, such as Budgeted Cost of Work Scheduled (BCWS) and drives the calculations for costs. ETC for a project is not scheduled on or before the As of Date.

    % Complete

    Defines the percent of work that has been completed on the project, based on the percentage of completion of the tasks and subprojects. This field is displayed only if the % Complete Calculation Method is set to Duration or Effort.

    Default: 0

    Values: 0 through 100

    % Complete Calculation Method

    Specifies the method to calculate the % Complete value for the project and tasks.

    Values:

    • Manual. Use this method to enter the % Complete for the project, summary, and detail tasks manually. Also, select this calculation method if you are using CA Clarity PPM with Microsoft Project, or if you are using an external job to calculate % Complete. The % Complete field appears on the task properties page.
    • Duration. Use this method to track the % Complete based on the duration. The duration is a measure of the total span of active working time for a task: from the start date to the finish date of a task. The % Complete for summary tasks is automatically calculated based on the following formula:
      Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
      
    • Effort. Use this method to calculate the % Complete for summary and detail tasks, automatically, based on the work units that are completed by resource assignments. If you assign a nonlabor resource to a task, the effort and actuals for that resource are ignored in the calculation. The calculations are based on the following formulas.
      Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort
      Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
      

    Default: Manual

    Note: Set the % Complete Calculation Method at the beginning of your project and do not change this value.

    Important! Verify that the start and finish dates of tasks and assignments are the same or within the start and finish dates of the project. Else, the start and end dates of the project are automatically redefined as per the start and end dates of the tasks and assignments.

  4. Complete the fields in the Tracking section. The following fields require explanation:
    Track Mode

    Indicates the tracking method that is used by resource assignments to enter time spent on project tasks.

    Values:

    • Clarity. Resource assignments enter time against their assigned tasks using timesheets.
    • None. Resources other than labor resources track actuals from financial transaction records or through a desktop scheduler, such as Open Workbench and Microsoft Project.
    • Other. Actuals are imported from a third-party application.

    Default: Clarity

    Charge Code

    Defines the charge code against which transactions for the project are charged. If you also define task-level charge codes on timesheets, then the task charge codes override this code.

  5. Select the Prevent Unassigned Timesheet Tasks check box if you do not want to allow users to add unassigned timesheet tasks to the project.
  6. Complete the fields in the Staffing section. The following fields require explanation:
    Default Staff OBS Unit

    Defines the set default OBS unit that is used when you add team staff members to this project. This OBS unit describes a staffing requirement, and can be a resource pool, a specific location, or a department. By mapping roles with OBS units and resource managers, the roles can be filled more accurately. The default staff OBS unit is used during capacity planning for analyzing demand against your capacity using the staff OBS as filter criteria.

    For more information about managing resources, see the Resource Management User Guide.

    Example:

    Use the OBS to find out if you have enough capacity for programmers in Atlanta to fulfill the demand for programmers in that location.

  7. Save your changes.

Define the Risk Properties

You can rate the risk for a project from a predefined list of risk factors by severity level.

Follow these steps:

  1. Open the project, and from Properties, click Risk.
  2. Rate the project risk by selecting the options for the Contributing Factors.
  3. Save your changes.

Define the Budget Properties

Budget information is essential in managing and analyzing portfolios. Correctly defining and recording planned cost and benefit information help to assess and analyze projects.

Note: To see all data from an investment to a portfolio, your CA Clarity PPM administrator must run the Synchronize Portfolio Investment job.

With a budget, you can define metrics, such as the Net Present Value (NPV) of the project, Return on Investment (ROI), and breakeven information. You can also define project planned and budgeted costs and benefits over a specified time period.

Alternatively, you can define a detailed financial plan to budget costs and benefits over multiple periods. If you create a detailed financial plan, information from the detailed plan is automatically populated in the budget properties page.

Follow these steps:

  1. Open the project.
  2. Open the Properties menu, and from Properties, click Budget.
  3. Complete the fields in the Budget Properties page. The following fields require explanation:
    Budget Equals Planned Values

    Indicates whether you want the budget cost and benefit values to be equal to the planned cost and budget values. If you clear this check box, you can manually define the budget values.

  4. Save your changes.

Define Project Dependencies

Dependency relationships can exist between one investment and another in your portfolio. Use the Properties: Dependencies page for the investment to identify this relationship.

Dependencies can occur between the start and completion of conflicting work effort, or from budget overruns. From this page, you can do the following tasks:

Follow these steps:

  1. Open the project.
  2. Open the Properties menu, and from Properties, click Dependencies.
  3. Select a mode to view or add the following:
  4. Click Add to add more dependencies to your investment.
  5. Select an investment type from the Type drop-down, select an investment, and click Add.

Create the Project Team

Project members and tasks are the core elements of a project. Both are essential to meeting project objectives. You can build a project team with the following members:

Team Staff

The resources that the project manager assigns to tasks and performs the work. Team staff members are allocated to the project. A team staff member can consist of labor, materials, equipment, and expense resource or role types. You can include resources other than labor resources or roles to process financial transactions against them.

Participants

The resources that the project manager adds to the project. Participants can view the project properties, generate ideas, and monitor progress. By default, team staff members become automatic participants. However, you can also add resources that are not team staff members as participants on the project. The value selected for the Automatically Add Staff Members As Investment Participant option determines whether the team staff member automatically becomes a participant.

Participant Groups

A group of resources who are project participants.

Add Resources or Roles

When necessary, add resources or roles to your project as team staff members. You can add resources or roles to a project automatically when you assign them to a project task in the work breakdown structure (WBS) in the Gantt view.

Follow these steps:

  1. Open the project and click Team.
  2. Click Add.
  3. Select the resources or roles to add to the project staff, and click Add.
  4. Save your changes.

More information:

About Team Staff Member OBS Unit

Define the Resource Allocation

When necessary, define the resource allocations for the resources that you have staffed to the project. The Project Team Staff page lists the booking status for all the investments to which the resource is allocated. In addition, you can see the number of hours the resource is allocated to each investment and displays a list of planned and committed allocation for the project. This information helps you determine the resource availability for a project, or to determine when a resource is overbooked or under-booked and by how much. Unless you change the booking dates, the resource is automatically staffed to the project for the duration of the project.

Use the time-scaled column in the list to change most of the time-related values for the resources on the project. Allocation by resource, allocation, and time period is displayed in this column. You can edit information such as the time cells for each resource. Changing the time cells changes the way that planned and committed allocation is presented in the time-scaled column.

Follow these steps:

  1. Open the project and click Team.
  2. Complete the fields in the Project Team Staff page for the required team members. The following fields require explanation:
    Booking Status

    Defines the booking status for the resource.

    Values:

    • Soft. The resource is tentatively scheduled to work on the investment.
    • Hard. The resource is committed to work on the investment.
    • Mixed. The resource is both soft and hard allocated to the investment, or the soft allocation for the resource does not match the hard allocation.

    Default: Soft

    % Allocation

    Defines the expected percentage of time for the resource to work (as tentative or committed) on the investment. The product assumes that each team staff member is assigned to the project and to each task at 100 percent of their available time. This assumption is true if the resource is not allocated to other tasks on other projects.

  3. Save your changes.

More information:

How to Define Project Estimates (ETC)

Create Project Tasks

A project includes multiple tasks, which are activities that begin and end on defined dates.

You can create tasks using the following methods:

Note: This scenario does not explain all of the methods to create a task. For more information about creating tasks, see the Project Management User Guide.

You can create the following types of project tasks:

Milestone

A milestone task indicates a critical point in a project, such as the completion of the first phase of the execution.

Specifies a major event or activity in a project and it indicates the phase completion or major deliverables or any significant achievement of your project during the execution of the project.

In the project plan, any task with zero duration is a milestone. That is, the Start date and Finish dates are the same for milestone tasks. Once saved, the Start field on the task properties page is locked.

Key Task

Specifies whether you want to identify a task as a key task. A key task is significant for other tasks. For example, the start date of other tasks can depend on the key task.

Example: If a task is one in which the completion is essential to the start date of other tasks, then mark this task as a key task.

Default: Selected

Fixed Duration

Specifies the fixed length of working time between the start and finish of a task. The duration for the task remains at the value you enter and the application recalculates the resource units as you change assignments.

Before building your work breakdown structure (WBS), plan the tasks and structure to help ensure effective use.

Note: For new projects, a new empty row (task) appears, by default, in the WBS. When you configure the Gantt view to not display all of the required fields, an initial blank task for projects without tasks does not appear. In addition, you cannot perform inline edits.

A summary task includes subtasks and summaries of those subtasks. For example, a project can have the creation of a new division as a summary task and the training of new staff as a subtask. Dependencies can be among, and outside, tasks in the projects.

Insert a Task to a Specific WBS Location

When necessary, insert a task to a specific location in the work breakdown structure (WBS) in the Gantt view.

Follow these steps:

  1. Open the project.
  2. Open the Tasks menu and click Gantt.
  3. Select the check box against the project name, or click anywhere on the task row to insert the new task row below it. Then, perform one of these actions:
  4. Complete the fields in the Create Tasks page. The following fields require explanation:
    % Complete

    Defines the percent of work that has been completed when the task is partially completed.

    Values:

    • Zero. The task is not started.
    • 1 through 99. The task has ETC or actuals posted and the task is not started.
    • 100. The task is complete.

    Default: 0

  5. Perform one of the following actions:

Copy a Task from a Project Template

You can copy predefined tasks from a project template into your project. The process copies all the estimating, risk, and issue information that is associated with the tasks.

Follow these steps:

  1. Open the project.
  2. Open the Tasks menu and click Gantt.
  3. Click the down arrow for the Create New Task icon on the Gantt view, and click Copy Task from Template.
  4. Select the project template containing the tasks and click Next.
  5. Select the tasks to copy into your project.
  6. Click Copy.

Manage Resource Utilization

Resource utilization is the amount of resource effort it takes, or is expected to take, to complete a task. Using the Project: Tasks: Resource Utilization page, you can do the following tasks:

By default, the Gantt chart displays total effort by task by week for all of the resources assigned to that task. You can change the chart configuration to display different variations of task and resource information.

Important! Assign staff to tasks before viewing resource utilization.

Follow these steps:

  1. Open the project.
  2. Open the Tasks menu and click Resource Utilization.
  3. Edit the following fields:
    Task

    Defines the task name. Click the task name to open the task properties page.

    ID

    Defines the task unique identifier (up to 16 characters).

    Start

    Defines the date to start working on the task.

    Default: Current date

    Note: Work on a task cannot start before the project start date. If the task has already started or finished, this field is not available.

    Finish

    Defines the date for completing the task.

    Default: Current date

    Note: Work on a task cannot finish after the project finish date. If the task has already started or finished, the field is not available.

  4. Save your changes.

Assign Resources

Assign labor resources to tasks so that they can perform work and record the work time in their timesheets.

You can also assign expense, material, and equipment resources to tasks. These types of resources can also be tracked using timesheets, and can have actuals that are logged through transactions.

Note: You cannot assign resources to milestone or summary tasks.

Assign Resources to the Project Tasks

Using the task assignments page, you can view a list of resources that are assigned to a task.

Follow these steps:

  1. Open the project and click Tasks.
  2. Open the Tasks menu and click Assignments.
  3. Perform one of the following actions from the Task Assignments page:
    1. Replace resources that are assigned to a task.
    2. Remove resources that are assigned to a task.
    3. Assign resources to a task from the Gantt view.

Assign Resources from the Gantt View

You can assign resources to detail tasks from the work breakdown structure (WBS) in the Gantt view using one of the following methods:

Note: You can only assign resources to detail tasks.

The assignment pool setting for the project determines the resources that you can assign to a task. The product supports the following assignment pool settings:

Resource Pool

Select from a general list of resources accessible to you. When you assign a resource from outside the project team, the resource is added to the project team as a staff member.

Team Only

Select from the available resources on the project team. The team members must be in the project staff before you can assign a task to them.

Project Templates

You can create projects from project templates based on standard task and role assignments based on a project type. Templates help ensure consistency and efficiency in creating projects.

Use a project template to copy the contents of the template into a new project instead of creating a project from scratch. You can also scale the overall project work estimate and budget. To scale, you require using a specified percentage rather than copying the contents of a template project as is. You can modify any of the information in the new project that is copied from the template.

You can change project templates to suit the needs of your organization. You can also duplicate templates to create new ones for each project type.

More information:

Managing Projects

Designate Projects as Project Template

Populate Projects from a Template

How to Copy Financial Plans from Project Templates

Designate Projects as Project Template

To make project creation more efficient, as a project owner, designate a project as a project template. Then, use the template to create new projects.

Before designating a project as a project template, verify that the following conditions are true:

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Complete the following field:
    Template

    Specifies using the project as a project template to create other projects.

    Default: Cleared

    Required: No

    Select the check box.

  3. Save the changes.

More information:

Financial Processing (Investments)

Financially Close Projects

Populate Projects from a Template

Populate Projects from a Template

To populate a new project, copy the information from an existing template. For example, you can copy the following types of information:

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Actions menu on the top right side of the page, and click Copy Project from Template.

    The select project template page appears.

  3. Select the button next to the project template, and click Next.

    The copy template options page appears.

  4. Complete the following fields:
    Template Name

    Displays the name of the project template from which data is used to populate the new project. Use a template to create a project with the following types of information predefined:

    • Project roles
    • Work breakdown structure
    • Financial plans
    • Project documents

    A template enables you to implement projects with common elements throughout the organization.

    not sure if we need to describe all this in the field definition. this info is already provided in the conceptual text that precedes the procedure and the field descriptions

    Scale Work By

    Defines the percentage by which the work estimate on each task is required to be increased or decreased for the new project. The scaling is relative to the template.

    Values: 0-100 (where zero means no change)

    Default: Zero

    Scale Budget By

    Defines the percentage (positive or negative) as the scaling factor for the dollar amounts defined in the project cost plans and benefit plans.

    Values: 0-100 (where zero means no change)

    Default: Zero

    Example: The template project from 1/1/2012 to 12/31/2012 allocates $10,000 for planned cost and $20,000 for planned benefit for the project duration. If a Scale Budget By value of 20 percent is defined, the plans copy over to the new project as follows. Assume that the project duration is same as the template project:

    • The planned cost shows $12,000 (scaled up by an extra 20 percent of the original value).
    • The planned benefit shows $24,000 (scaled up by an extra 20 percent of the original value).
    Convert resources to roles

    Specifies to replace the resources in the new project with the primary roles, or team roles of the named resources on the project template. If a named resource has no primary role or team role, the named resource is retained on the new project. This setting overrides the default project management setting on the settings page.

    For example, a cost plan uses a resource as a grouping attribute. When you select this check box, the cost plan from the template is copied. However, the resource values are not converted to roles. The resource value can be the only value that differentiates one line item detail row from another. In the absence of the value, duplicate detail rows can result in the cost plan.

    Default: Cleared

  5. Click Copy.

More information:

Scheduling (projects)

Managing Projects

Rules for Copying Financial Plans from Project Templates

The following rules apply when you copy financial plans from a template to a new or existing project:

More information

By Example: How Start Dates of Financial Plans are Copied Over

Financially Enable Projects

Project Fields Used for Copying Financial Plans

When copying financial plans from a project template, some of the fields from your first-created project are used. The following fields in the template project affect how the financial plans are copied over to a new project:

Start Date

The time periods on the financial plans that are copied over from the project template shift in the new project according to this start date. The End Date field value in the project template is not relevant to financial plans. The end date is automatically calculated for each financial plan based on their original plan durations in the template and their new start dates.

Set Planned Cost Dates

This field is only considered when no budget plans exist in the project template. Selecting the option retains the same dates for planned cost and planned benefit on the budget properties page as the project start and end dates. If unselected, the dates for planned cost and planned benefit are shifted. The shifting is based on the difference between the template project start date and the new project start date.

Department

The following rules apply to the department OBS:

Scale Budget By

Defines the percentage (positive or negative) as the scaling factor for the dollar amounts defined in the project cost plans and benefit plans.

Values: 0-100 (where zero means no change)

Default: Zero

Example: The template project from 1/1/2012 to 12/31/2012 allocates $10,000 for planned cost and $20,000 for planned benefit for the project duration. If a Scale Budget By value of 20 percent is defined, the plans copy over to the new project as follows. Assume that the project duration is same as the template project:

More information:

Financial Processing (Investments)

Define Financial Properties (Investments)

How to Work with Project Properties

By Example: How Start Dates of Financial Plans are Copied Over

This example shows how the start and end time periods are set for financial plans that you create by copying from a template project.

The template project with a start date in December 2010 includes the following financial plans:

When you copy the template information into a new project with a start date in December 2011, the financial plans shift. Financial plans shift according to the new start date. But the plans maintain the same time lapse between the start and end dates originally defined in the template.

The financial plans now have the following new start and end time periods:

How to Copy Financial Plans from Project Templates

Use the following process to copy financial plans from project templates:

  1. Create the fiscal time periods that include the start dates of the template and target projects.

    For more information, see the Financial Management User Guide.

  2. Do one of the following:

More information:

Populate Projects from a Template

Financial Processing (Investments)

How to Work with Project Properties

Project properties comprise the following:

With the project open, access the links to define project characteristics.

You can:

Edit General Properties (Investments)

Edit the general properties of any project to which you have access.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Complete the following fields in the General section:
    Assignment Pool

    Specifies the pool of resources that is allowed when assigning resources to tasks.

    Values:

    • Team Only. Allow only staff members.
    • Resource Pool. Allow team staff members and resources for whom you have access rights to book to a project. With this option, when you assign a resource to a task, the resource is also added as a team staff member.

    Default: Resource Pool

    Project Name

    Defines the name for the project.

    Limits: 80 characters

    Required: Yes

    Project ID

    Defines the unique identifier for the project that is typically auto-numbered.

    Limits: 20 characters

    Required: Yes

    Description

    Defines the description.

    Limits: 240 characters

    Required: No

    Manager

    Specifies the name of the resource that is responsible for managing the project. The manager of a project automatically receives certain rights for the project.

    The project manager is not the same as the collaboration manager. The person creating the project becomes the collaboration manager for the project by default.

    Default: The resource creating the project. If you are creating a project that someone else can manage, change the default to another resource.

    Required: No

    Page Layout

    Specifies the page layout to view project information. Available layouts are company-specific and dependent on the values set by your CA Clarity PPM administrator. Layouts also depend on whether an add-in is installed. If other layouts are not available, the field is display only.

    Default: Project Default Layout

    Required: Yes

    Risk

    Displays the project risk status in the form of a stoplight. The stoplight colors are based on your selections on the main risk page. If you have detailed risks defined, the colors are derived from the risks page.

    Values:

    • Green = Low Risk
    • Yellow = Medium Risk

    Red = High Risk

    Goal

    Specifies the purpose or business case for this project.

    Values: Cost Avoidance, Cost Reduction, Grow the Business, Infrastructure Improvement, and Maintain the Business

    Required: No

    Alignment

    Specifies the alignment with corporate objectives. Displays a stoplight that indicates the project alignment status.

    Values:

    • 66 - 100 (Green) = Aligned
    • 33 - 65 (Yellow) = Alignment at risk
    • 0 - 32 (Red) = Out of alignment
    • Required: No
    Status

    Indicates the status of the investment.

    Values: Approved, Rejected, Unapproved

    Default: Unapproved

    Active

    Specifies if the investment is active. Activate the investment to enable posting transactions. Also, to view the investment in capacity planning portlets.

    Default: Selected

    Program

    Specifies using a program to create projects.

    Default: Cleared

    Required: No

    Template

    Specifies using the project as a project template to create other projects.

    Default: Cleared

    Required: No

    Required

    Specifies to pin this investment when added to a portfolio. This field is used during scenario generation.

    Default: Cleared

    Required: No

    For more information, see the Portfolio Management User Guide.

  3. In the Organizational Breakdown Structures section, define the OBS to associate with the project for security, organizational, or reporting purposes.

    For more information, see the Basics User Guide.

    Organizational

    Defines the lines of business for your organization that is responsible for the proposal.

    Department

    Defines the financial department associated with the investment.

    Required: No

    For more information, see the Financial Management User Guide.

    This OBS is listed last if more than one OBS exists.

    Location

    Defines the financial location that is associated with the investment. This location must belong to the same entity as the department.

  4. Save the changes.

More information:

Risks, Issues, Change Requests, and Action Items

Financially Enable Projects

Financial Processing (Investments)

Risk Rating

Financial Processing (Investments)

You can process financial transactions for your project. But, before processing financial transactions, enable your project to set up financial transaction defaults, such as specifying the project and cost matrices. The selections automatically populate transaction entries upon selecting the project.

More information:

How to Set up Projects for Financials

Define Financial Properties (Investments)

Financially Enable Projects

Financially Close Projects

How to Set Up Projects for Tracking Costs

Financially Close Projects

How to Set up Projects for Financials

To set up a project for financial processing, set up the following:

Define Financial Properties (Investments)

Use the following process to define the financial properties used in summary and detailed financial planning.

If the following conditions are true, when changing the financial status of a project from Open to Hold or Closed, an error message appears:

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Properties, click Financial.
  3. In the General section, complete the following fields:
    Company Name

    Defines the customer (internal or external) that drives rates and costs. You require creating a company profile.

    Project ID

    Defines the unique identifier for the project that is typically auto-numbered.

    Limits: 20 characters

    Required: Yes

    Affiliated Project

    Defines the project that is financially tied to the project.

    Department

    Defines the financial department associated with the investment.

    Required: No

    For more information, see the Financial Management User Guide.

    Location

    Defines the financial location that is associated with the investment. This location must belong to the same entity as the department.

    Financial Status

    Specifies the status that determines how financial transactions entered against the project are handled.

    Values:

    • Open. All transactions entered against the project can be fully processed. Use the financial status to open it for financial processing, or to enable the project financially.
    • Hold. New transactions cannot accumulate on the project.
    • Closed. New transactions cannot accumulate. When you mark the project financial status as "Closed", it is no longer open for financial processing.

    Default: Hold

    Required: Yes

    Investment Financial Type

    Defines the billing method required for financial transaction processing.

    Values:

    • Standard. Standard bills let transactions accumulate over a given cycle and let you charge resulting transactions at any time.
    • Internal. Used to track financial transactions that are not meant for chargebacks.

    Default: Standard

    Required: Yes

    For more information, see the Financial Management User Guide.

    WIP Class

    Defines the transaction category used to group projects for reporting.

    Investment Class

    Defines the class used to group projects for reporting purposes.

    Billing Currency Code

    Defines the currency that is used to process chargebacks and financial transactions on the project. After you process transactions or create detailed financial plans for the project, you cannot change this currency code value.

  4. In the Labor Transaction Rates, Material Transaction Rates, Equipment Transaction Rates, and Expense Transaction Rates sections, enter the following cost or rate information as needed:
    Rate Source

    Defines the cost/rate matrix used to calculate the benefit amount of the transaction entry.

    Cost Source

    Defines the cost/rate matrix used to calculate the cost amount of the transaction entry.

    Exchange Rate Type

    Displayed only when multiple currencies are available. Defines the exchange rate type for transactions for the project. When the project is approved, you cannot modify the exchange rate type.

    Values:

    • Average. The blended derived rate over a period: weekly, monthly, or quarterly.
    • Fixed. The fixed rate that does not change over a defined period.
    • Spot. The variable rate that changes frequently, say daily.
  5. Save the changes.

More information:

Financial Processing (Investments)

How to Set up Projects for Financials

Financially Enable Projects

Financially Close Projects

How to Set Up Projects for Tracking Costs

Financially Enable Projects

To use detailed financial planning and process financial transactions, financially enable your project.

For more information, see the Financial Management User Guide.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Properties, click Financial.
  3. Complete the following fields:
    Department

    Defines the financial department associated with the investment.

    Required: No

    For more information, see the Financial Management User Guide.

    Location

    Defines the financial location that is associated with the investment. This location must belong to the same entity as the department.

    Financial Status

    Specifies the status that determines how financial transactions entered against the project are handled.

    Values:

    • Open. All transactions entered against the project can be fully processed. Use the financial status to open it for financial processing, or to enable the project financially.
    • Hold. New transactions cannot accumulate on the project.
    • Closed. New transactions cannot accumulate. When you mark the project financial status as "Closed", it is no longer open for financial processing.

    Default: Hold

    Required: Yes

    Select the "Open" status.

  4. Save the changes.

Financially Close Projects

Financially closing a project helps ensure that additional funds are not assigned to the project.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Properties, click Financial.

    The financial page appears.

  3. Complete the following field:
    Financial Status

    Specifies the status that determines how financial transactions entered against the project are handled.

    Values:

    • Open. All transactions entered against the project can be fully processed. Use the financial status to open it for financial processing, or to enable the project financially.
    • Hold. New transactions cannot accumulate on the project.
    • Closed. New transactions cannot accumulate. When you mark the project financial status as "Closed", it is no longer open for financial processing.

    Default: Hold

    Required: Yes

  4. Save the changes.

More information:

Financial Processing (Investments)

How to Set up Projects for Financials

Define Financial Properties (Investments)

Financially Enable Projects

How to Set Up Projects for Tracking Costs

Deactivate Projects

Mark Projects for Deletion

Financial Processing (Investments)

How to Set Up Projects for Tracking Costs

Use the following process to set up projects for tracking costs:

  1. Create and define one or more financial cost matrices.

    For more information, see the Financial Management User Guide.

  2. Create a project.
  3. Financially enable the project.
  4. Set the project earned value (EV) calculation method.
  5. Associate the cost matrix to the project resource types.
  6. Assign staff to project tasks.
  7. Create a cost plan using the team allocations.

    For more information, see the Financial Management User Guide.

  8. Schedule the Cost/Rate Matrix Extraction job to run periodically.

    Contact your CA Clarity PPM administrator or see the Administration Guide for more information.

  9. Baseline the project.
  10. Calculate and record earned value information.
About the Financial Cost/Rate Matrix

The financial cost/rate matrix is used for tracking purposes. You can associate the matrix to your project so that budgeted cost of work performed (BCWP) and earned value (EV) information is calculated. You can associate the financial cost matrix at the project level for labor, material, and equipment resources, and for expenses incurred against your projects.

The financial cost matrix is also used when you generate reports containing certain project cost information. To enable the values to calculate, assign resources or roles to tasks. Also, have your CA Clarity PPM administrator schedule the Rate Matrix Extraction job to run periodically.

Contact your CA Clarity PPM administrator or see the Administration Guide for more information.

If you do not associate the financial cost, or rate matrix to the project, your finance manager requires specifying a cost when creating transactions.

For more information, see the Financial Management User Guide.

More information:

How to Set Up Projects for Tracking Costs

Associate the Financial Cost/Rate Matrix to Projects

How to Update Cost Totals

Associate the Financial Cost/Rate Matrix to Projects

Use this procedure to associate the financial cost matrix to a project resource type. The financial cost matrix is used to calculate project rates.

Important! Before you can associate the financial cost matrix to your project, create the matrix.

For more information, see the Financial Management User Guide.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Properties, click Financial.

    The financial properties page appears.

  3. In the Labor Transaction Rates, Material Transaction Rates, Equipment Transaction Rates, and Expense Transaction Rates sections, enter the following cost information:
    Rate Source

    Defines the cost or rate matrix used for calculating the benefit amount of the transaction entry.

    Cost Source

    Defines the cost or rate matrix used for calculating the cost amount of the transaction entry.

    Exchange Rate Type

    Displayed only when multiple currencies are available. Defines the exchange rate type that is used for transactions entered against the project. When the project is approved, you cannot modify the exchange rate type.

    Values:

    • Average. The blended derived rate over time, typically weekly or monthly.
    • Fixed. The fixed rate that does not change over a defined period.
    • Spot. The variable rate that changes over the course of a day.
  4. Save the changes.

More information:

How to Set Up Projects for Tracking Costs

About the Financial Cost/Rate Matrix

Earned Value

Control Access to Projects

Use the Access to This Project pages to view, grant, and edit the instance-level access rights to your project. You can view access rights on the full view page. You can also edit and grant access rights on the resource, group, and OBS unit pages.

Estimate to Complete (ETC) (Investments)

The Estimate to Complete (ETC) is the estimated time for a resource to complete an assignment. The value is important for both project planning and revenue recognition. In the short run, estimates help project managers more effectively allocate work hours. In the end, project managers can compare estimates to actuals, which can help produce more accurate forecasting and planning.

The estimating properties display the current and new ETC values. To view the page, open the project, click the Properties menu, and click Estimating.

You can do the following from this page:

More information:

How to Define Project Estimates (ETC)

How Estimates (ETC) are Calculated

How to Modify ETC (Investments)

How to Define Project Estimates (ETC)

The following process outlines how to define the estimates for a project:

  1. Assign resources to the tasks.
  2. Generate the estimates.
  3. Define estimates:
  4. Define allocations by individual resource.

How Estimates (ETC) are Calculated

When you assign a resource to a task, the estimate to complete (ETC) for the task is automatically calculated. Allocation (percent) and availability (Hours) for a resource assignment determines the ETC for the task based on the assignment start and finish dates. The calculation is based on the following formula:

ETC = the number of working days the resource is assigned to work on the task * the number of hours each day that the resource is available for work

The calendar and daily availability for a resource is used to determine the total availability for the resource. Unless you specify a different number in the resource profile, eight hours of work time are available daily, by default, for each resource is assumed.

Example 1

You allocate Aaron Connors 100 percent to a project and assign him to a task for 5 days with 8 hours availability. The ETC for Aaron is 40 hours. You allocate Patty Chen 50 percent to a project and assign her to the same task for 5 days. The ETC for Patty is 20 hours.

Example 2

You schedule a task between 6/30/11 and 7/30/11. The task contains 22 working days and has one resource assigned to it for 8 hours a day for all 22 days. The ETC for the task is calculated at 176 hours (22 days * 8 hours each day). You assign two resources to the task, each with a total daily availability of 8 hours. One resource for 50 percent of the available time and the other resource for 100 percent. The combined ETC calculates to 264.

For more information about managing resources, see the Resource Management User Guide.

More information:

Allocations

About Assigning Resources to Tasks

How to Modify ETC (Investments)

You can change the project-level ETC in the following ways:

Important! Assign staff to tasks before you can view and edit ETC.

Apply New ETC Across Tasks

You can apply estimates (ETC) across all tasks by editing and applying the ETC at the project level. Applying ETC at the project level distributes the ETC value across all the project tasks according to task duration, resource availability, and resource allocation. The current ETC assumes the new value.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu and click Estimating.

    The estimating properties page appears.

  3. Complete the following field:
    New ETC

    Defines the new estimate to apply across all the tasks in the project.

  4. Click Apply.

    The new ETC is applied.

Apply ETC (Investments)

Use this procedure to view and edit the combined ETC of all the tasks in the project and to apply ETC. The estimating page displays a breakdown of project ETC by phase or task grouping. You can expand the list to view the ETC for each task in the phase or group. Once a project or task is underway, ETC reflects the number of remaining hours estimated to complete the project.

To apply top-down estimating, enter the percentage share of the top-down estimate distributed for each task.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu and click Estimating.

    The estimating properties page appears.

  3. Complete the following fields:
    Mode

    Specifies the mode for estimating.

    Values:

    • Top-Down Estimating. Use this mode to specify a percentage of the estimates for tasks.
    • Estimating Rules. Use this mode to estimate rules for applying estimates to tasks.

    Default: Top-Down Estimating

    Current ETC

    Displays the current estimate to complete (ETC) for the project. The value for this field is derived from the Current ETC on the estimating properties page.

    Required: No

    New ETC

    Defines the new estimate to apply across all the tasks in the project.

  4. Click Preview.

    The list of tasks display.

  5. View the following fields:
    Task

    Defines the name of the task. Clicking the plus sign or summary task name displays subtasks below the summary task.

    ID

    Displays the unique identifier for the task.

    Current ETC

    Displays the total Estimate To Complete (ETC) for the task. The value for this field is derived from the ETC field on the task estimating properties page.

    Top-down %

    Displays the percentage of the top-down estimate from the project that is distributed to the task.

    New ETC

    Displays the new estimate to apply to the task.

  6. Click Apply.

    The ETC is distributed to the tasks set up to receive the top-down distribution.

More information:

How to Modify ETC (Investments)

Apply New ETC Across Tasks

How Estimates (ETC) are Calculated

How to Set Up Tasks for Top-Down Estimating

Labor Effort Portlet

Subprojects

Use sub projects to group related projects under one master project for scheduling purposes. Establishing sub project associations lets you create plans and track and analyze an individual project in detail. The associations also help viewing, summarizing, and analyzing the progress of several projects at the master project level. You can use master projects with subprojects to perform top-down planning and to share resource availability across projects.

Subprojects are allocated at 100 percent to the master project, and participate in the master project baseline and earned value metrics. You cannot change the allocation percentages.

You can associate any number of projects together. Information is not shared between the subprojects and the master project, or between the subprojects themselves.

Example

You create a master project named Database Reconstruction which contains three subprojects: Oracle, Sybase, and FoxPro.

More information:

Add Subprojects to Master Projects

Create Subprojects from Project Templates

Create Subprojects

View Combined Subproject Actuals and Estimates (projects)

Control Access to Subprojects

About Updating Master Project Baselines

Add Subprojects to Master Projects

Use the following procedure to add an existing subproject to a master project. You can add an unlimited number of subprojects to a master project.

Use the properties page, or Gantt view to add a project as a subproject. You can open a subproject from the master project and modify it.

Follow these steps:

  1. Open the project to create subprojects under it.

    The properties page appears.

  2. Open the Properties menu, and from Main, click Subprojects.

    The subprojects properties page appears.

  3. Select the check box next to the project to add as a subproject, and click Add.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Tasks menu and click Gantt.

    The Gantt view appears.

  3. Click the Add Existing Subproject icon in the Gantt view.

    The select subprojects page appears.

  4. Select the check box next to the project to add as a subproject, and click Add.

Create Subprojects from Project Templates

Use this procedure to create a subproject using a project template. The default field values, defined in the project template, vary depending on the selections made in the template.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Tasks menu and click Gantt.

    The Gantt view appears.

  3. Click the down arrow for the Add Existing SubProject icon in the Gantt view, and click Create New Project From Template.

    The available project templates appear.

  4. Select a project template and click Next.

    The create page appears.

  5. Complete the following fields in the General section:
    Assignment Pool

    Specifies the pool of resources that is allowed when assigning resources to tasks.

    Values:

    • Team Only. Allow only staff members.
    • Resource Pool. Allow team staff members and resources for whom you have access rights to book to a project. With this option, when you assign a resource to a task, the resource is also added as a team staff member.

    Default: Resource Pool

    Project Name

    Defines the name for the project.

    Limits: 80 characters

    Required: Yes

    Project ID

    Defines the unique identifier for the project that is typically auto-numbered.

    Limits: 20 characters

    Required: Yes

    Description

    Defines the description.

    Limits: 240 characters

    Required: No

    Manager

    Specifies the name of the resource that is responsible for managing the project. The manager of a project automatically receives certain rights for the project.

    The project manager is not the same as the collaboration manager. The person creating the project becomes the collaboration manager for the project by default.

    Default: The resource creating the project. If you are creating a project that someone else can manage, change the default to another resource.

    Required: No

    Page Layout

    Specifies the page layout to view project information. Available layouts are company-specific and dependent on the values set by your CA Clarity PPM administrator. Layouts also depend on whether an add-in is installed. If other layouts are not available, the field is display only.

    Default: Project Default Layout

    Required: Yes

    Start Date

    Defines the initial start date for a project. As you create tasks and assignments, this date is auto-calculated to match the first date that a task is scheduled to start. At that point, to edit this date, adjust the following dates:

    • Start date of the first task of the project.
    • Start date of the resource assignments and allocations on the project.

    Important! Verify that the start dates of tasks and assignments are the same or later than the start date of the project. Else, the start date of the project is automatically redefined as per the start dates of the tasks and assignments.

    Default: Current date

    Required: Yes

    Finish Date

    Defines the initial finish date for a project. As you create tasks and assignments, this date is auto-calculated to match the last date that a task is scheduled to finish. At that point, to edit this date, adjust the following dates:

    • End date of the first task of the project.
    • End date of the resource assignments and allocations on the project.

    Important! Verify that the finish dates of tasks and assignments are the same or before the finish date of the project. Else, the end date of the project is automatically redefined as per the end dates of the tasks and assignments.

    Default: Current date

    Set Planned Cost Dates

    Specifies if the planned cost dates are synchronized with the investment dates. Selecting the option for a detailed financial plan does not affect the planned cost dates.

    Default: Selected

    Stage

    Defines the stage in the investment lifecycle. The list of choices is company-specific and depends on the values that your administrator sets.

    The metric is used in portfolio analysis when you use comparable stage criteria across all portfolio investments.

    Goal

    Specifies the purpose or business case for this project.

    Values: Cost Avoidance, Cost Reduction, Grow the Business, Infrastructure Improvement, and Maintain the Business

    Required: No

    Priority

    Defines the relative importance of this investment in relation to all other investments. The priority controls the order in which tasks are scheduled during autoscheduling. The priority is subject to dependency constraints.

    Values: 0 - 36 (where zero is the highest importance)

    Default: 10

    Required: No

    Progress

    Indicates the level of work that is completed on the tasks.

    Values:

    • Completed (100 percent)
    • Started (1 - 99 percent)
    • Not Started (0 percent)

    Default: Not Started

    Required: Yes

    Status

    Indicates the status for the project.

    Values: Approved, Unapproved, and Rejected

    Default: Unapproved

    Required: Yes

    Required

    Specifies to pin this investment when added to a portfolio. This field is used during scenario generation.

    Default: Cleared

    Required: No

    For more information, see the Portfolio Management User Guide.

    % Complete Calculation Method

    Specifies the method to calculate the % Complete value for the project and tasks.

    Values:

    • Manual. Use this method to enter the % Complete for the project, summary, and detail tasks manually. Also, select this calculation method if you are using CA Clarity PPM with Microsoft Project, or if you are using an external job to calculate % Complete. The % Complete field appears on the task properties page.
    • Duration. Use this method to track the % Complete based on the duration. The duration is a measure of the total span of active working time for a task: from the start date to the finish date of a task. The % Complete for summary tasks is automatically calculated based on the following formula:
      Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
      
    • Effort. Use this method to calculate the % Complete for summary and detail tasks, automatically, based on the work units that are completed by resource assignments. If you assign a nonlabor resource to a task, the effort and actuals for that resource are ignored in the calculation. The calculations are based on the following formulas.
      Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort
      Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
      

    Default: Manual

    Note: Set the % Complete Calculation Method at the beginning of your project and do not change this value.

  6. Complete the following fields in the Organization Breakdown Structures section:
    Department

    Defines the department OBS for the project.

    Location

    Defines the location OBS for the project.

  7. Complete the following fields in the Copy Template Project Options section:
    Template Name

    Displays the name of the project template from which data is used to populate the new project. Use a template to create a project with the following types of information predefined:

    • Project roles
    • Work breakdown structure
    • Financial plans
    • Project documents

    A template enables you to implement projects with common elements throughout the organization.

    not sure if we need to describe all this in the field definition. this info is already provided in the conceptual text that precedes the procedure and the field descriptions

    Scale Work By

    Defines the percentage by which the work estimate on each task is required to be increased or decreased for the new project. The scaling is relative to the template.

    Values: 0-100 (where zero means no change)

    Default: Zero

    Scale Budget By

    Defines the percentage (positive or negative) as the scaling factor for the dollar amounts defined in the project cost plans and benefit plans.

    Values: 0-100 (where zero means no change)

    Default: Zero

    Example: The template project from 1/1/2012 to 12/31/2012 allocates $10,000 for planned cost and $20,000 for planned benefit for the project duration. If a Scale Budget By value of 20 percent is defined, the plans copy over to the new project as follows. Assume that the project duration is same as the template project:

    • The planned cost shows $12,000 (scaled up by an extra 20 percent of the original value).

    The planned benefit shows $24,000 (scaled up by an extra 20 percent of the original value).

    Convert resources to roles

    Specifies to replace the resources in the new project with the primary roles, or team roles of the named resources on the project template. If a named resource has no primary role or team role, the named resource is retained on the new project. This setting overrides the default project management setting on the settings page.

    For example, a cost plan uses a resource as a grouping attribute. When you select this check box, the cost plan from the template is copied. However, the resource values are not converted to roles. The resource value can be the only value that differentiates one line item detail row from another. In the absence of the value, duplicate detail rows can result in the cost plan.

    Default: Cleared

  8. Save the changes.

More information:

Subprojects

Add Subprojects to Master Projects

Create Subprojects

View Combined Subproject Actuals and Estimates (projects)

Control Access to Subprojects

Rules for Copying Financial Plans from Project Templates

Create Subprojects

Use this procedure to create a subproject from the work breakdown structure of the master projects.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Tasks menu and click Gantt.

    The Gantt view appears.

  3. Click the down arrow for the Add Existing Subproject icon in the Gantt view, and click Create New Project.

    The create page appears.

  4. Complete the following fields:
    Assignment Pool

    Specifies the pool of resources that is allowed when assigning resources to tasks.

    Values:

    • Team Only. Allow only staff members.
    • Resource Pool. Allow team staff members and resources for whom you have access rights to book to a project. With this option, when you assign a resource to a task, the resource is also added as a team staff member.

    Default: Resource Pool

    Project Name

    Defines the name for the project.

    Limits: 80 characters

    Required: Yes

    Project ID

    Defines the unique identifier for the project that is typically auto-numbered.

    Limits: 20 characters

    Required: Yes

    Description

    Defines the description.

    Limits: 240 characters

    Required: No

    Manager

    Specifies the name of the resource that is responsible for managing the project. The manager of a project automatically receives certain rights for the project.

    The project manager is not the same as the collaboration manager. The person creating the project becomes the collaboration manager for the project by default.

    Default: The resource creating the project. If you are creating a project that someone else can manage, change the default to another resource.

    Required: No

    Page Layout

    Specifies the page layout to view project information. Available layouts are company-specific and dependent on the values set by your CA Clarity PPM administrator. Layouts also depend on whether an add-in is installed. If other layouts are not available, the field is display only.

    Default: Project Default Layout

    Required: Yes

    Start Date

    Defines the initial start date for a project. As you create tasks and assignments, this date is auto-calculated to match the first date that a task is scheduled to start. At that point, to edit this date, adjust the following dates:

    • Start date of the first task of the project.
    • Start date of the resource assignments and allocations on the project.

    Important! Verify that the start dates of tasks and assignments are the same or later than the start date of the project. Else, the start date of the project is automatically redefined as per the start dates of the tasks and assignments.

    Default: Current date

    Required: Yes

    Finish Date

    Defines the initial finish date for a project. As you create tasks and assignments, this date is auto-calculated to match the last date that a task is scheduled to finish. At that point, to edit this date, adjust the following dates:

    • End date of the first task of the project.
    • End date of the resource assignments and allocations on the project.

    Important! Verify that the finish dates of tasks and assignments are the same or before the finish date of the project. Else, the end date of the project is automatically redefined as per the end dates of the tasks and assignments.

    Default: Current date

    Set Planned Cost Dates

    Specifies if the planned cost dates are synchronized with the investment dates. Selecting the option for a detailed financial plan does not affect the planned cost dates.

    Default: Selected

    Stage

    Defines the stage in the investment lifecycle. The list of choices is company-specific and depends on the values that your administrator sets.

    The metric is used in portfolio analysis when you use comparable stage criteria across all portfolio investments.

    Goal

    Specifies the purpose or business case for this project.

    Values: Cost Avoidance, Cost Reduction, Grow the Business, Infrastructure Improvement, and Maintain the Business

    Required: No

    Priority

    Defines the relative importance of this investment in relation to all other investments. The priority controls the order in which tasks are scheduled during autoscheduling. The priority is subject to dependency constraints.

    Values: 0 - 36 (where zero is the highest importance)

    Default: 10

    Required: No

    Progress

    Indicates the level of work that is completed on the tasks.

    Values:

    • Completed (100 percent)
    • Started (1 - 99 percent)
    • Not Started (0 percent)

    Default: Not Started

    Required: Yes

    Status

    Indicates the status for the project.

    Values: Approved, Unapproved, and Rejected

    Default: Unapproved

    Required: Yes

    Required

    Specifies to pin this investment when added to a portfolio. This field is used during scenario generation.

    Default: Cleared

    Required: No

    For more information, see the Portfolio Management User Guide.

    % Complete Calculation Method

    Specifies the method to calculate the % Complete value for the project and tasks.

    Values:

    • Manual. Use this method to enter the % Complete for the project, summary, and detail tasks manually. Also, select this calculation method if you are using CA Clarity PPM with Microsoft Project, or if you are using an external job to calculate % Complete. The % Complete field appears on the task properties page.
    • Duration. Use this method to track the % Complete based on the duration. The duration is a measure of the total span of active working time for a task: from the start date to the finish date of a task. The % Complete for summary tasks is automatically calculated based on the following formula:
      Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
      
    • Effort. Use this method to calculate the % Complete for summary and detail tasks, automatically, based on the work units that are completed by resource assignments. If you assign a nonlabor resource to a task, the effort and actuals for that resource are ignored in the calculation. The calculations are based on the following formulas.
      Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort
      Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
      

    Default: Manual

    Note: Set the % Complete Calculation Method at the beginning of your project and do not change this value.

  5. In the Organizational Breakdown Structures section, define the OBS to associate with this project for security, organizational, or reporting purposes.

    For more information, see the Basics User Guide.

  6. Save the changes.

View Combined Subproject Actuals and Estimates (projects)

You can view combined subproject actuals and estimates for all the master project subprojects using the properties page of subprojects.

The following list describes the columns and data that display on this page:

Project

Displays the project name and links to the project properties.

ID

Displays the project ID that is typically autonumbered.

Count

Indicates the number of subprojects for a subproject (or for a program, a project).

Actuals

Displays the actuals that are posted for the tasks in each subproject. The value in the Total cell reflects the combined actuals for all the project subprojects.

ETC

Displays the subproject estimate to complete. The Estimate to Complete (ETC) is the estimated time for a resource to complete an assignment. The value in the Total cell reflects the combined ETC for all the subprojects.

Total Effort

Displays the subproject total effort based on the following formula:

Total Effort = Actuals + Remaining ETC

The value in the Total cell reflects the combined effort for all the project subprojects.

Percent Expended

Displays the percentage of resource usage expended on the subproject. The value in the Total cell reflects the combined percentage for all the project subprojects.

Baseline

Displays the subproject usage value for the most current baseline based on the following formula:

Usage = Total Effort (Actuals + Remaining ETC) to date
Total

Displays a stoplight indicator with the subproject overall approval status.

Read Only

Specifies if the subproject is accessible to project participants as read-only.

Control Access to Subprojects

By default, all project participants have read/write access to any subproject added to the project. However, you can change the access settings of individual subprojects to read-only. You can also change the ones set to read-only back to read/write.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu and click Subprojects.

    The list page appears.

  3. Select the check box next to the subproject to limit access, and click Set Read-Only.

    The subproject is now only accessible to project participants as read-only. A check appears in the Read Only column for that subproject.

Follow these steps:

  1. Open the project to set access to the subproject.

    The properties page appears.

  2. Open the Properties menu and click Subprojects.

    The list page appears.

  3. Select the check box next to the subproject, and click Set Read/Write.

    The subproject is now accessible to project participants as read/write. A check disappears from the Read Only column for that subproject.

Baselines

Baselines are snapshots of the total actual and planned effort and total actual and planned cost estimates for a project at the moment of capture. They are static. The changes you make to your project after you create your baseline do not affect the current baseline. You explicitly update a baseline to reflect changes to project scope or cost.

You can view baseline cost and work allocation information. Also, you can view other information, such as earned value (EV) and project performance that is most relevant to your project and organization. View the information about the baseline properties page and on the baseline revision properties page.

More information:

Create New Baselines (Investments)

Edit Baselines (Investments)

Define the Current Baseline (Investments)

Update Project Baselines

Update Task Baselines

Subproject Baselines

Earned Value Metrics

Create New Baselines (Investments)

You can create baselines for the entire project from the baseline properties page, or from the work breakdown structure (WBS) page. This procedure details how to create a baseline from the baselines page.

You can create an unlimited number of project baselines. Create an initial baseline before resources enter time on a project. After the initial baseline, you can create additional ones at various intervals. You can create a baseline midway through the project, when different phases complete, or at the end of the project.

The project must be unlocked before you can create a baseline. To perform detailed baselining, open the project in a desktop scheduler, such as Open Workbench or Microsoft Project.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Main, click Baseline.

    The baseline properties page appears.

  3. Click New.

    The baseline revision properties page appears.

  4. Complete the following fields:
    Revision Name

    Defines the name of the baseline revision.

    Example:

    Initial Baseline, Mid-Term Baseline, or Final Baseline.

    Required: Yes

    Revision ID

    Defines the unique identifier for the baseline revision.

    Example:

    The baseline version number, such as v1 or v5.

    Required: Yes

    Description

    Defines the description for the baseline revision.

    Required: No

    Current Revision

    Specifies to make this baseline the current baseline. The field is display only if a baseline revision exists.

    Default: Selected

  5. Save the changes.

More information:

Baselines

Edit Baselines (Investments)

Define the Current Baseline (Investments)

Update Project Baselines

Update Task Baselines

Subproject Baselines

How Master Project and Subproject Baselines Work

Unlock and Hold Locks on Projects (Microsoft Project)

Unlock Projects in Tentative Schedule Mode

About Project Locks (Microsoft Project)

Baselines

Edit Baselines (Investments)

Edit baselines from the baseline properties page. You can edit the revision name, revision ID, and description. You can also delete baselines. If you delete the current baseline and another baseline revision exists, the remaining baseline becomes the current revision.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Main, click Baseline.

    The baseline properties page appears.

  3. Click the name of the baseline revision.

    The baseline revision properties page appears.

  4. Complete the following fields:
    Current Revision

    Specifies to make this baseline the current baseline. The field is display only if a baseline revision exists.

    Default: Selected

    Revision Name

    Defines the name of the baseline revision.

    Example:

    Initial Baseline, Mid-Term Baseline, or Final Baseline.

    Required: Yes

    Revision ID

    Defines the unique identifier for the baseline revision.

    Example:

    The baseline version number, such as v1 or v5.

    Required: Yes

    Description

    Defines the description for the baseline revision.

    Required: No

    Start

    Displays the project or task start date at the time you create the baseline. The value for the field is taken from the start date field on the scheduling properties page.

    Finish

    Displays the project or task finish date at the time you take the baseline. The value for the field is taken from the finish date field on the scheduling properties page.

    Usage

    Displays the system-generated usage at the time you take for baselining using the following formula:

    Usage = Total of Actuals + ETC
    In lists and in portlets, the usage field displays the value from baseline usage field on the revision properties page.
    
    BCWP

    Displays the system-calculated value of Budgeted Cost of Work Performed (BCWP). The value is calculated and recorded when you baseline a project, or when you update earned value totals. BCWP is also referred to as the earned value (EV). BCWP represents the amount of the budgeted cost (BAC) completed based on performance as measured using the Task EV Calculation method.

    Calculations are made based on the level at which the calculation is made. BCWP is calculated at the following levels:

    • Task. BCWP is based on the selected EV calculation method.
    • Project. BCWP is the sum of BCWP for all WBS Level 1 tasks in the project.

    Current Baseline Required: Yes

  5. Save the changes.

More information:

Baselines

Define the Current Baseline (Investments)

Define the Current Baseline (Investments)

Use the following procedure to define a baseline revision as the current baseline. You can view the current baseline revision from the baseline properties page. A checkmark icon displays in the Current Revision field for the current revision. By default, the baseline you create last becomes the current project baseline. If you have defined only one baseline, that becomes the current baseline.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Main, click Baseline.

    The baseline properties page appears.

  3. Complete the following field:
    Current Revision

    Specifies to make this baseline the current baseline. The field is display only if a baseline revision exists.

    Default: Selected

    Select the check box.

  4. Save the changes.

More information:

Edit Baselines (Investments)

Update Project Baselines

Use this procedure to update master project and subproject baselines. You can update existing project baselines to reflect changes to task assignments and other information, such as recently posted actuals. When you update a baseline, it becomes the current baseline revision.

When you update a project baseline, the changes to task assignments, estimates, and the financial summary from the last update get included. Updating a baseline changes its values accordingly.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Main, click Baseline.

    The baseline properties page appears.

  3. Select the check box next to the baseline to update, and from the Actions menu, click Update Baseline.

    The confirmation page appears.

  4. Click Yes.

More information:

Baselines

Create New Baselines (Investments)

Edit Baselines (Investments)

Define the Current Baseline (Investments)

Update Task Baselines

Subproject Baselines

Update Task Baselines

About Updating Master Project Baselines

Update Task Baselines

Use this procedure to update the current baseline for a specific task. You can select an unlimited number of tasks from the list. When you update the task baseline, the changes to assignments and estimates from the last baseline update get included. Financial summary changes are not included.

Follow these steps:

  1. Open the project and click Tasks.

    The list page appears.

  2. Open the Tasks menu and click Gantt.

    The Gantt view appears.

  3. Select the check box next to the task to update. Click the down arrow for the Create Baseline icon in the Gantt view, and click Update Task Baseline.

    The confirmation page appears.

  4. Click Yes.

More information:

Baselines

Update Project Baselines

Define the Current Baseline (Investments)

Subproject Baselines

The master project baseline information is an aggregation of its own baseline information and subprojects. The baseline is dynamically aggregated at the time you set the baseline. The master project resource baseline information is an aggregation of the team baseline information.

More information:

How Master Project and Subproject Baselines Work

About Updating Master Project Baselines

Display Master Project Baselines

Baselines

Update Project Baselines

How to Calculate and Record Earned Value Totals

How Master Project and Subproject Baselines Work

When you open a baselined master project and add a new subproject, the current baseline for the subproject is saved. When you baseline the master project, the new baseline replaces the subproject baseline. The baseline becomes the current baseline for the master project. The subproject information is aggregated and rolled up to the master project baseline.

If subprojects of the master project have more than one baseline, the current baseline displays in views. The subproject baseline inherits the name and the ID of the master project baseline. If the subproject already has a baseline with the same ID, that baseline is updated and a new baseline is not created. The link between the master project baseline and the subproject baseline is created based on the baseline ID. The baseline ID is shared between the two baselines.

When you delete a master baseline, the subproject baseline is also deleted.

More information:

Edit Baselines (Investments)

About Updating Master Project Baselines

When you update the baseline for a master project, the baselines for each subproject are also updated. The baseline becomes the current baseline for the master project and its subprojects.

Subproject Baseline Information Roll up

When you update a subproject baseline, baseline and earned value (EV) information are not rolled up. To update the master project roll up the baseline information from the sub projects.

More information:

Subproject Baselines

How to Calculate and Record Earned Value Totals

Display Master Project Baselines

Suppose, you open a master project that is not baselined, but have baselined one of the subprojects. The current baseline for the subproject is displayed in views.

Example

You have a master project with two subprojects, SB1 and SB2, and only SB1 has a current baseline, Baseline1. You rename Baseline1. You baseline a selected task in SB2. You delete SB1 baseline and replace it with SB2 baseline. SB2 baseline is the current revision.

More information:

Subproject Baselines

Baselines

Edit Baselines (Investments)

Define the Current Baseline (Investments)

Earned Value

Earned value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for a scheduled activity or work breakdown structure. Earned value is also referred to as the budgeted cost of work performed (BCWP).

You can use the EV information to review historical performance and to predict future performance.

More information:

About Default Earned Value Options (Investments)

Earned Value Metrics

How to Calculate and Record Earned Value Totals

About Earned Value Calculation Methods

How Earned Value Calculation Methods are Applied

Earned Value Reporting Periods

About Default Earned Value Options (Investments)

About Default Earned Value Options (Investments)

If your organization uses earned value management methodology for measuring project performance, you can set the project-level default earned value calculation method. Use the fields in the Earned Value section of the scheduling properties page to set the method. You can also use this page to associate your project to an earned value reporting period.

The earned value reporting period defines the frequency and the interval for the Update Earned Value History job. The job takes historical earned value snapshots of performance and saves them in the earned value history table. When using earned value methodologies to analyze project performance, the job uses the earned value reporting period to take the snapshot. It saves the snapshot based on the project association to the period. The project manager associates the project to the appropriate period.

More information:

Scheduling (projects)

Earned Value

How to Calculate and Record Earned Value Totals

Set the Default Earned Value Options (Tasks)

How Earned Value Calculation Methods are Applied

Earned Value Metrics

You can use the earned value (EV) fields to track work performance to account for cost and schedule variances. Baseline information is factored in to the calculations performed in earned value analysis. All earned value fields contain the fundamental calculations used for earned value analysis (EVA).

The following EV values are calculated for every scheduled activity:

BAC

Displays the system-calculated value of Budget at Completion (BAC), which is the budgeted total cost at the time of the baseline. This value is calculated based on the following formula:

BAC = ((Actuals + Remaining Work) x Billing Rate) taken at time of baseline

Current Baseline Required: Yes

BCWS

Displays the system-calculated value of Budgeted Cost of Work Scheduled (BCWS). BCWS is the budgeted amount to spend on the project in a given time period. If not specified, the date is either the current date for the project, or the system date. BCWS is also referred to as the planned value (PV).

The BCWS is calculated based on the following formula:

BCWS = Sum of BAC through a point in time

Current Baseline Required: Yes

ACWP

Displays the system-calculated value of Actual Cost of Work Performed (ACWP), which is the total direct cost incurred in performing work based on posted actuals. ACWP is calculated at the following levels:

Current Baseline Required: No

BCWP

Displays the system-calculated value of Budgeted Cost of Work Performed (BCWP). The value is calculated and recorded when you baseline a project, or when you update earned value totals. BCWP is also referred to as the earned value (EV). BCWP represents the amount of the budgeted cost (BAC) completed based on performance as measured using the Task EV Calculation method.

Calculations are made based on the level at which the calculation is made. BCWP is calculated at the following levels:

Current Baseline Required: Yes

EAC

Displays the aggregated total for the cost of all actuals over time.

EAC (T)

Displays the system-calculated value of Estimate At Completion (EAC). This calculation is most often used when current variances are seen as typical of future variances. The calculation is based on the following formula:

EAC (T) = ACWP + ETC

Current Baseline Required: No

EAC (AT)

Displays the system-calculated value of estimate at completion (EAC). This calculation is most often used when current variances are seen as atypical. And the project management team expectations are that similar variances will not occur in the future. The calculation is based on the following formula:

EAC (AT) = (ACWP + (BAC - BCWP))

Current Baseline Required: Yes

ETC (AT)

Displays the system-calculated value of estimate at completion (ETC) using earned value data. This calculation is most often used when current variances are seen as atypical. And the project management team expectations are that similar variances will not occur in the future. The calculation is based on the following formula:

ETC (AT) = BAC - BCWPc

Current Baseline Required: Yes

ETC (Cost)

Displays the system-calculated value of Estimate To Completion (ETC), and is calculated based on the following formula:

ETC (Cost) = remaining labor cost + remaining non-labor cost

Current Baseline Required: No

ETC (T)

Displays the system-calculated value of estimate at completion (ETC) using earned value data. This calculation is most often used when current variances are seen as typical of future variances. This value is calculated based on the following formula:

ETC (T) = (BAC - BCWPc)/CPIc

Current Baseline Required: Yes

The following values are used together to determine if work is performed as planned. The most frequently employed measures are:

CV

Displays the system-calculated value of Cost Variance (CV). The CV is the value of what is accomplished to date as opposed to what is spent to date. The calculation is based on the following formula:

CV = BCWP - ACWP

Current Baseline Required: Yes

SV

Displays the system-calculated value of Schedule Variance (SV). The SV is the value of what is scheduled to date as opposed to what is performed to date. A positive value indicates that the work is ahead of the baseline schedule. A negative value indicates that the work is behind the baseline schedule. The calculation is based on the following formula:

SV = BCWP - BCWS

Current Baseline Required: Yes

CPI

Displays the system-calculated value of Cost Performance Index (CPI), which is an efficiency rating for work accomplished. A value equal to or greater than one indicates a favorable condition. A value less than one indicate an unfavorable condition. The calculation is based on the following formula:

CPI = BCWP / ACWP

Current Baseline Required: Yes

SPI

Displays the system-calculated value of Schedule Performance Index (SPI), which is the ratio of work performed to work scheduled. A value less than one indicate the work is behind schedule. The calculation is based on the following formula:

SPI = BCWP / BCWS

Current Baseline Required: Yes

More information:

Scheduling (projects)

Earned Value

How to Calculate and Record Earned Value Totals

How to Calculate and Record Earned Value Totals

Follow these steps:

  1. Select the earned value calculation method:
  2. Baseline your project if you want those earned value fields that require Budget at Completion (BAC) as input for earned value analysis calculated.
  3. Do one of the following:

About Earned Value Calculation Methods

An earned value calculation method is the method for calculating the various earned value (EV) metrics. Some of the methods are system calculated. For methods that are not system calculated, manually enter the Budgeted Cost of Work Performed (BCWP) for your project.

If you use an EV calculation method for your project and all of its tasks that are not system calculated, define your project BCWP value. To define the value, baseline the project or updating the earned value totals. You can also override BCWP for specific tasks.

Regardless of the earned value calculation method you set for your project, the value entered in the BCWP Override field overrides the system-calculated BCWP values. The value is used in all EV calculations that require BCWP as a parameter.

The following EV calculation methods are available:

Percent Complete (PC)

Defines an estimate expressed as a percent of the amount of work that has been completed on a task or work breakdown structure. The EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following formula:

BCWP = Budget at Completion (BAC) * % complete
0/100

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following fixed formula:

If % complete = 100, then BCWP = Budget at Completion (BAC); otherwise, BCWP = zero.

Use this method when project work begins and completes in a single reporting period. Also, use when credit is only earned when the project or task is 100 percent complete.

50/50

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following formula:

If % complete > zero but < 100, then BCWP = Budget at Completion (BAC) / 2. If % complete = 100, then BCWP = BAC. If % complete = zero, then BCWP = zero.

Use this method when project work begins and completes within two reporting periods. Also use when 50 percent credit is earned when a project or task is started and the remaining 50 percent is earned upon completion.

Level of Effort (LOE)

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following formula:

BCWP = Budgeted Cost of Work Scheduled (BCWS)
Weighted Milestones

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is user-defined. The project manager assigns weights to milestones across the duration of the summary task. As each milestone in the summary task is reached, a specific percent of the work is completed until 100 percent is reached. Use this method if your organization uses earned value management methodology for measuring project performance and has projects and tasks that use this method. When you use this method, you enter the BCWP at the task level. Use the BCWP Override field in the Earned Value section of the task properties page.

Milestone Percent Complete (PC)

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is not system calculated but user-defined. Dollar amounts are selected for the weighting of each time period, instead of a percentage. EV credit is earned as a percent of the milestone value assigned. Use this method if your organization uses earned value management methodology for measuring project performance and has projects and tasks that use this method. When you use this method, you enter the BCWP at the task level. Use the BCWP Override field in the Earned Value section of the task properties page.

Apportioned Effort (AE)

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is not system calculated but is user-defined. Task work effort is tied to other task work efforts. As the base task completes work, the apportioned task earns completed work. The task uses the work effort tied to other tasks to drive its performance. Use this method for discrete work that is related to other discrete work. Use this method if your organization uses earned value management methodology for measuring project performance and has projects and tasks that use this method. When you use this method, you enter the BCWP at the task level. Use the BCWP Override field in the Earned Value section of the task properties page.

More information:

Earned Value

How to Set Up Projects for Tracking Costs

Set the Default Earned Value Options (Tasks)

Create New Baselines (Investments)

How to Calculate and Record Earned Value Totals

How Earned Value Calculation Methods are Applied

By default, the earned value (EV) calculation method for projects and tasks is percent complete. If your organization uses earned value management methodology for measuring project performance, your CA Clarity PPM administrator can change the default earned value calculation method setting. Change the setting to the method your company uses for projects and tasks.

Best Practice: Have your CA Clarity PPM administrator define the object-level default setting for projects and tasks. In this way, the EV calculation method defaults to this object-level setting when you create new projects or tasks.

You can override the object-level EV calculation method setting at the project and at the task level. When calculating the earned value metrics, the EV calculation method setting you establish at the task level is used. The results are rolled up to the project. If you do not define a method for the task, the task inherits the method from its parent task. If you do not define the method for the summary task, it inherits the method value from the project. If you do not set the method for the project, the task is ignored when the earned value is calculated.

If you create projects from project templates, you can set the EV calculation method in the project template. The projects, created from the template, inherit the setting.

Note: If you are using CA Clarity PPM with Microsoft Project and specify an earned value calculation method other than percent complete, use CA Clarity PPM to calculate, display, and report earned value metrics.

More information:

About Default Earned Value Options (Investments)

Earned Value Metrics

How to Calculate and Record Earned Value Totals

About Earned Value Calculation Methods

Set the Default Earned Value Calculation Method

About Earned Value Calculation Methods

About Default Earned Value Options (Investments)

Set the Default Earned Value Options (Tasks)

How to Close Projects

Use the following process to close projects:

How to Delete Projects

The following process outlines how to delete a project:

  1. Verify that the project contains no posted transactions.

    For more information, see the Financial Management User Guide.

  2. Verify that the project contains no time entries with a value greater than zero.
  3. Financially close the project.
  4. Deactivate the project.
  5. Mark the project for deletion.

    For more information, see the Basics User Guide.

  6. If necessary, cancel the deletion process before running the job.
  7. Schedule the Delete Projects job to run.

    Note: Your CA Clarity PPM administrator schedules and runs the job on a regular basis.

    For more information, see the Administration Guide.

Deactivate Projects

Active projects display by default on the projects list page. Deactivate a project before removing it from the list of active projects. A deactivated project can be reactivated again.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Complete the following field:
    Active

    Specifies if the investment is active. Clear the check box to deactivate the investment.

    Default: Selected

  3. Save the changes.

More information:

How to Delete Projects

Mark Projects for Deletion

How to Close Projects

Open Projects from CA Clarity PPM in Microsoft Project

Mark Projects for Deletion

You can mark a project for deletion only when the project is inactive. Projects so marked remain listed on the projects list page until the Delete Investments job runs.

Follow these steps:

  1. Open Home, and from Portfolio Management, click Projects.

    The list page appears.

  2. Expand the filter and filter the list for inactive projects.

    The inactive projects display in the list.

  3. Select the check box next to the project, and click Mark for Deletion.

    The confirmation page appears.

  4. Click Yes.

More information:

Deactivate Projects

Cancel Projects Marked for Deletion

You can cancel projects marked for deletion when the following conditions are true:

When you cancel an inactive project marked for deletion, the project is not deleted when the Delete Investments job runs. Inactive projects continue to appear in the list of inactive projects.

Follow these steps:

  1. Open Home, and from Portfolio Management, click Projects.

    The list page appears.

  2. Expand the filter and filter the list for inactive projects.

    A list of inactive projects displays on the projects list page.

  3. Select the check box next to the project and click Cancel Deletion.

    The confirmation page appears.

  4. Click Yes.