Previous Topic: ProgramsNext Topic: Portlets and Reports


Project Setup

This section contains the following topics:

How to Set Up Timesheets

About Input Type Codes

About Invalid Transactions

How to Work with Project Management Settings

About Base Calendars

Risk Category Types

About the Risk Score Matrix

Earned Value Reporting Periods

Earned Value Periods

How to Set Up Timesheets

Complete the following setup before staff members can track time and project managers can view and approve timesheets:

Set Timesheet Options

Follow these steps:

  1. Open Administration, and from Project Management, click Timesheet Options.

    The timesheet options page appears.

  2. In the Default Content and Layout section, do the following:
  3. Click Apply.
  4. Complete the following fields:
    Default Sorting Column

    Specifies the default sort column.

    Values: Investment and Description

    Default: Investment

    Sorting Order

    Defines the sorting order.

    Values: Ascending or Descending

    Default: Ascending

  5. In the Default Time Entry Options section, complete the following fields:
    Disable Indirect Time Entries

    Specifies to disable the entering of indirect time.

    Default: Cleared

    Required: No

    Populate Time Range

    Defines the number of days before the time begins for the resources to start entering timesheets.

    Example: Suppose, you set days before the time start to “14” and days after time period end to “10” for the resources to enter their timesheet. The timesheet is populated with tasks 14 days before the period begins and 10 days after the time period ends.

    Default: 7

    Required: No

    User Value 1

    Displays the first user value for the plan.

    Detail Object: Internal User Value 1 ID

    User Value 1 Lookup

    Select the first user value lookup for time entry.

    Auto-Populate

    Specifies your auto-populate timesheet options.

    Values:

    • Off. Requires resources to always manually enter all items on timesheets.
    • Copy time entries from previous timesheet. Allows resources to populate timesheets with tasks from the resource previous timesheet automatically.
    • Copy time entries from previous timesheet and include actuals (actuals not copied for incidents). Allows resources to enter timesheets with tasks and actuals from previous timesheets automatically.

    Default: Off

    Required: No

    Display Unit

    Specifies how to display resource time.

    Values: Hours and Days

    Default: Hours

    Required: No

    Decimal Places

    Specifies the number of decimal places to use when reporting hours and days.

    Values: 0, 1, 2, 3, 4, and 5

    Default: 2

    Required: No

    Enable Note Date

    Specifies to allow users to enter a date on a time entry note indicating the date to which the note refers.

    Default: Cleared

    Required: No

  6. Save the changes.

About Time Reporting Periods

Before you can perform financial planning tasks, such as determining actuals on tasks, first create the time reporting periods. Resources use the reporting periods when entering the time they spend on tasks in their timesheet.

For more information, see the Financial Management User Guide.

How to Work with Time Reporting Periods

You can do the following to work with time reporting periods:

Create Time Reporting Periods

Before resources can enter their time, specify the beginning and ending date for each time reporting period. A time reporting period cannot have an overlapping start and finish dates with another period type and year. Each time reporting period you create must have a unique period name, period type, year, and period number.

Follow these steps:

  1. Open Administration, and from Project Management, click Time Reporting Periods.

    The time reporting periods page appears.

  2. Click New.

    The properties page appears.

  3. Complete the following fields:
    Scale

    Specifies the time duration for the reporting period.

    Values: Annual, Monthly, Quarterly, Semiannual, Weekly, Daily, or Biweekly

    Default: Weekly

    Start Date

    Specifies the start date for the reporting period.

    Finish Date

    Specifies the finish date for the reporting period. Click the calendar icon, select an end date for the new time period, then click Add.

  4. Save the changes.
Edit Time Reporting Periods

You can change time reporting periods that are unused. Used time reporting periods are locked and cannot be changed.

Follow these steps:

  1. Open the time reporting period.

    The properties page appears.

  2. Edit the following fields:
    Period Name

    Defines a unique name for the period.

    Period Type

    Defines the time reporting period type.

    Values: Weekly, 13 Periods per Year, Monthly, Quarterly, and Annually

    Period Number

    Indicate the order of the time reporting period to appear (in ascending order).

    Example: First (“1”), second (“2”), or third (“3”).

    Description

    Defines the description of the period.

    Quarter

    Specifies the quarter associated with the period for roll-up purposes.

    Year

    Defines the year associated with the period for roll-up purposes.

    Start Date

    Specifies the start date for the reporting period.

    Finish Date

    Specifies the finish date for the reporting period. Click the calendar icon, select an end date for the new time period, then click Add.

  3. Save the changes.
How to Delete Time Reporting Periods

Use the following process to delete a time reporting period:

  1. Verify that a resource does not enter time for the time reporting period and the period is unlocked.
  2. Mark the time reporting period for deletion.
  3. If necessary, cancel the deletion process before the job run.
  4. Have your CA Clarity PPM administrator schedule to run the Delete Investments job on a regular basis.

    For more information, see the Administration Guide.

Mark Time Reporting Periods for Deletion

You can mark a time reporting period for deletion only when the reporting period is unlocked. Time reporting periods that you mark for deletion are not deleted until the Delete Investments job runs.

You can only delete time reporting periods that you create. You cannot delete static time reporting periods.

Follow these steps:

  1. In the time reporting list, select the check box next to the time period, and click Mark for Deletion.

    The confirmation page appears.

  2. Click Yes.

More information:

How to Delete Time Reporting Periods

Cancel the Deletion of Time Reporting Periods

You can cancel time reporting periods marked for deletion when the following conditions are true:

When you cancel a time reporting period marked for deletion, the reporting period is not deleted when the Delete Investments job runs.

Follow these steps:

  1. Open Administration, and from Project Management, click Time Reporting Periods.

    The time reporting periods page appears.

  2. Select the check box next to the time reporting period and click Cancel Deletion.

    The confirmation page appears.

  3. Click Yes.

More information:

How to Delete Time Reporting Periods

About Charge Codes

Charge codes can represent any breakdown of work associated with investments, such as:

If you use financials, including transactions and timesheets, charge codes are required. If you do not require a charge code, close it for time entry.

For more information, see the Financial Management User Guide.

More information:

Create Charge Codes

Edit Charge Codes

Create Charge Codes

Follow these steps:

  1. Open Administration, and from Project Management, click Charge Codes.

    The list page appears.

  2. Click New.

    The charge code properties page appears.

  3. Complete the following fields:
    Charge Code Name

    Defines the name of the charge code.

    Required: Yes

    Charge Code ID

    Defines a unique identifier for the charge code.

    Required: Yes

    Open for Time Entry

    Specifies if the resource can track time spent on task assignments using timesheets. When cleared, the resource cannot log time on any project.

    Default: Selected

  4. Save the changes.

Edit Charge Codes

Follow these steps:

  1. Open the charge code.

    The properties page appears.

  2. Edit the following fields:
    Charge Code Name

    Defines the name of the charge code.

    Required: Yes

    Charge Code ID

    Defines a unique identifier for the charge code.

    Required: Yes

    Open for Time Entry

    Specifies if the resource can track time spent on task assignments using timesheets. When cleared, the resource cannot log time on any project.

    Default: Selected

  3. Save the changes.

About Input Type Codes

Input type codes represent a breakdown of work for cost associated with resources. They are used in transactions and in cost plans.

For more information, see the Financial Management User Guide.

Input type codes represent the resource that is doing the work rather than the investment from which work is initiated. Examples of input type codes include work performed, and regular as opposed to overtime hours.

You cannot delete input type codes. You can deactivate an input type code, so that it is not open for time entry.

More information:

Create Input Types

Edit Input Type Codes

Create Input Types

Follow these steps:

  1. Open Administration, and from Project Management, click Input Type Codes.

    The list page appears.

  2. Click New.

    The properties page appears.

  3. Complete the following fields:
    Name

    Defines the name of the input type code.

    Required: Yes

    ID

    Defines the unique identifier for the input type code.

    Required: Yes

    Active

    Indicates if the input type code is active.

    Default: Selected

    Required: No

    Chargeable

    Indicates if the input type code is chargeable. Chargeable codes help to process financial transaction and in financial planning, to track posted actuals.

  4. Save the changes.

Edit Input Type Codes

Follow these steps:

  1. Open the input type code to edit.

    The properties page appears.

  2. Edit the following fields:
    Name

    Defines the name of the input type code.

    Required: Yes

    ID

    Defines the unique identifier for the input type code.

    Required: Yes

    Active

    Indicates if the input type code is active.

    Default: Selected

    Required: No

    Chargeable

    Indicates if the input type code is chargeable. Chargeable codes help to process financial transaction and in financial planning, to track posted actuals.

  3. Save the changes.

About Invalid Transactions

Transactions can fail for various reasons. For example, a resource can enter an incorrect timesheet, causing a transaction to fail.

When transactions fail, you can view a list of invalid transactions on the invalid transactions page. To view a list of invalid transactions, click the Administration menu, and select Invalid Transactions from the Project Management menu.

How to Work with Project Management Settings

You can define the system level default project management options using the fields on the settings page. You can define the:

Defines the Default Project Management Settings

Use the project management settings page to set the system-level default project management options. For example, setting CA Clarity PPM to export only the current baseline when opening projects in a desktop scheduler (Open Workbench or Microsoft Project) from CA Clarity PPM.

Follow these steps:

  1. Open Administration, and from Project Management, click Settings.

    The settings page appears.

  2. Complete the following fields:
    Default Load Pattern

    Specifies the system-level default resource load pattern.

    Values: Back, Uniform, Fixed, Contour, or Front

    Default: Front

    Required: No

    Guidelines URL

    Specifies the URL for the guidelines.

    First Month of Financial Quarter

    Specifies the first month of the financial quarter.

    Values: All calendar months

    Default: January

    Required: No

    First Day of Work Week

    Specifies the first day of the workweek in the resource calendars and scheduler interfaces.

    Values: All calendar days

    Default: Monday

    Required: No

    Default Display Unit for Work Effort

    Specifies the default display unit for work effort.

    Values: Hours or Days

    Default: Hours

    Required: No

    Enable Investment-specific Charge Codes

    Specifies to allow entry of charge codes that are specific to investments.

    Default: Cleared

    Required: No

    Allow posting of future timesheets

    Specifies to allow the posting of future timesheets.

    Default: Selected

    Required: No

    Notify on Delete of Risk/Issue/Change Requests

    Defines whether you want a notification sent out whenever a resource deletes risks, issues, or change requests.

    Default: Cleared

    Required: No

    Only Export Current Baselines When Opening Investments in a Scheduler

    If you are using CA Clarity PPM with a desktop scheduler (Open Workbench or Microsoft Project), specifies to export only the current baseline in the desktop scheduler. This option applies when multiple baselines exist.

    Default: Cleared

    Required: No

    Round Allocations to Nearest %

    Specifies the amount you want allocations rounded to when booking resource time to projects.

    Default: 25

    Required: Yes

    Allow Effort Task Creation

    Specifies to create the effort task when you add a resource to a project does not have tasks.

    Default: Selected

    Required: No

    Reassign Tasks when replacing Role

    Specifies to allow tasks to be reassigned, or replaced when the project manager replaces a resource role.

    Default: Selected

    Required: No

    Allow Edit of Allocations when Investment is Locked

    Specifies to allow resources to edit allocations while projects are locked.

    Default: Cleared

    When selected, project managers can:

    • Edit existing team staff member allocations if the project is checked out in a desktop scheduler, such as Open Workbench or Microsoft Project.
    • Add new team staff members to the project.
    • Replace roles if the Reassign Tasks when replacing Role default project management setting is selected.

    Required: No

    Automatically Open Staff Members for Time Entry

    Defines if you want staff members to be open to enter time on project tasks after a specific action occurs.

    Values:

    • Never. Indicates that staff members are not automatically open for time entry to enter time on project tasks.

      Example: If you edit existing properties for a staff member, no changes are made to the Open for Time Entry value for the staff member. If you add new staff members, the Team object Open attribute Default value is used.

    • When Hard-Booked. Indicates that staff members are automatically open for time entry when they are hard-booked. Hard-booking here means when any amount is hard-booked, not when the booking status changes to "Hard".
    • When Request Status is Approved. Indicates that staff members are automatically open for time entry when their request status changes to “Approved.”

    Default: Never

    For more information, see the Studio Developer’s Guide.

    For more information about managing resources, see the Resource Management User Guide.

    Required: No

    Show Tasks in Organizer

    Defines how projects tasks are displayed in the Organizer.

    Values:

    • When Assigned. Indicates that project tasks are listed in the Organizer when resources are assigned to the task.
    • When Hard-Booked. Indicates that project tasks are listed in the Organizer when resources are hard-booked to the tasks.
    • When Request Status is Approved. Indicates that project tasks are listed in the Organizer when resources are approved.

    Default: When Assigned

    For more information, see the Basics User Guide.

    Required: No

    Automatically Add Staff Members As Investment Participant

    Specifies how resources are assigned to investments as participants.

    Values:

    • Never. Indicates that resources can never be automatically assigned to investments as participants.
    • When Added to Investment. Indicates that resources can be automatically assigned to investments as participants when they are added to these investments.

      If this option is selected and project notifications are enabled, project participants receive a project notification when added to the team staff page of a project.

    • When Hard Booked. Indicates that resources can be automatically assigned to investments as participants when they are hard-booked for these investments. Hard-booking here means when any amount is hard-booked, not when the booking status changes to "Hard".

    Default: When Added to Investment

    Required: No

    Allow Override Requisition Approval

    Specifies to allow project managers to require requisition approval on individual projects.

    Default: Cleared

    Note: If the project manager does not require requisition approval on a project. A project manager or resource manager requires the Project - Edit access right to book requisitions.

    Allow Mixed Booking

    Defines to let project managers edit the allocation of hard-booked resources, to mix booked resources on projects. Also, to extend a resource to do additional project planning.

    Default: Selected

    Note: If a mixed booking exists on the project, the field is read-only.

    Required: No

    Convert resources to roles when using templates (default)

    Specifies to convert all resources to project roles when the project manager creates a project from a project template.

    Note: The project manager can override this default setting when creating projects from project templates.

    Default: Cleared

    Required: No

    Requisition Booking

    Defines the options to book requisitions using allocation percentage or available work units. CA Clarity PPM decrements the requested amount based on the booked amount. To determine if a requisition is fully filled, depending on the selected booking option, CA Clarity PPM uses allocation percentage or time-varying values (work units).

    Values:

    • Use Allocation Percentage
    • Use Available Work Units

    Example: When using Allocation Percentage, a resource booked at 100 percent fully replaces another resource booked at 100 percent. The requisition is fully filled even if the hours they work per week are different. When using Available Work Units, if the new resource works fewer hours per week than the resource being replaced, the requisition is not fully filled.

  3. Save the changes.

More information:

How to Work with Project Management Settings

Baselines

About Resource Load Patterns

Autoschedule uses the resource load pattern to determine the ETC that is distributed for a resource over a set date range. You can establish the default resource load pattern at the system level and at the task assignment level. ETC is distributed first based on the resource load pattern defined at the task assignment level then at the system level.

You can select from one of the following load patterns:

Back

Work effort is loaded as close to the end of the task as possible, based on unused resource availability after autoscheduling. With this load pattern, ETC is only decremented when actuals are posted on unadjusted timesheets. The remaining ETC is spread out past the timesheet period based on the load pattern type.

Uniform

Work effort is loaded as evenly as possible based on total resource availability. With this load pattern, ETC is only decremented when actuals are posted on unadjusted timesheets. The remaining ETC is spread out past the timesheet period based on the load pattern type.

Fixed

Work effort distribution is user-defined. Autoschedule does not affect work effort distribution. With a Fixed load pattern, ETC is decremented through the timesheet period (that is, Actuals through Date) whether the resource posted actuals to the task.

Contour

Work effort is loaded as evenly as possible across the duration of the task, based on unused resource availability after autoscheduling. With this load pattern, ETC is only decremented when actuals are posted on unadjusted timesheets. The remaining ETC is spread out past the timesheet period based on the load pattern type.

If you are using CA Clarity PPM with Microsoft Project, when you open the project the first time from Microsoft Project, the work contour for the new assignments is set to flat. If you previously opened the assignment in Microsoft Project and saved it to CA Clarity PPM, the work contour in Microsoft Project does not change.

Front

Work effort is loaded as close to the start of the task as possible, based on unused resource availability after autoschedule. With this load pattern, ETC is only decremented when actuals are posted on unadjusted timesheets. The remaining ETC is spread out past the timesheet period based on the loading pattern type.

More information:

About Autoschedule

About Time-Varying ETCs for Assignments

Set the Default Resource Load Pattern

Use this procedure to set the system-level default resource load pattern. The load pattern you set on the settings page is used by default when project managers assign resources, or change staffing assignment properties.

Follow these steps:

  1. Open Administration, and from Project Management, click Settings.

    The settings page appears.

  2. Complete the following field:
    Default Load Pattern

    Specifies the system-level default resource load pattern.

    Values: Back, Uniform, Fixed, Contour, or Front

    Default: Front

  3. Save the changes.

About Earned Value Calculation Methods

An earned value calculation method is the method for calculating the various earned value (EV) metrics. Some of the methods are system calculated. For methods that are not system calculated, manually enter the Budgeted Cost of Work Performed (BCWP) for your project.

If you use an EV calculation method for your project and all of its tasks that are not system calculated, define your project BCWP value. To define the value, baseline the project or updating the earned value totals. You can also override BCWP for specific tasks.

Regardless of the earned value calculation method you set for your project, the value entered in the BCWP Override field overrides the system-calculated BCWP values. The value is used in all EV calculations that require BCWP as a parameter.

The following EV calculation methods are available:

Percent Complete (PC)

Defines an estimate expressed as a percent of the amount of work that has been completed on a task or work breakdown structure. The EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following formula:

BCWP = Budget at Completion (BAC) * % complete
0/100

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following fixed formula:

If % complete = 100, then BCWP = Budget at Completion (BAC); otherwise, BCWP = zero.

Use this method when project work begins and completes in a single reporting period. Also, use when credit is only earned when the project or task is 100 percent complete.

50/50

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following formula:

If % complete > zero but < 100, then BCWP = Budget at Completion (BAC) / 2. If % complete = 100, then BCWP = BAC. If % complete = zero, then BCWP = zero.

Use this method when project work begins and completes within two reporting periods. Also use when 50 percent credit is earned when a project or task is started and the remaining 50 percent is earned upon completion.

Level of Effort (LOE)

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is system calculated using the following formula:

BCWP = Budgeted Cost of Work Scheduled (BCWS)
Weighted Milestones

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is user-defined. The project manager assigns weights to milestones across the duration of the summary task. As each milestone in the summary task is reached, a specific percent of the work is completed until 100 percent is reached. Use this method if your organization uses earned value management methodology for measuring project performance and has projects and tasks that use this method. When you use this method, you enter the BCWP at the task level. Use the BCWP Override field in the Earned Value section of the task properties page.

Milestone Percent Complete (PC)

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is not system calculated but user-defined. Dollar amounts are selected for the weighting of each time period, instead of a percentage. EV credit is earned as a percent of the milestone value assigned. Use this method if your organization uses earned value management methodology for measuring project performance and has projects and tasks that use this method. When you use this method, you enter the BCWP at the task level. Use the BCWP Override field in the Earned Value section of the task properties page.

Apportioned Effort (AE)

Defines the EV calculation method where Budgeted Cost of Work Performed (BCWP) is not system calculated but is user-defined. Task work effort is tied to other task work efforts. As the base task completes work, the apportioned task earns completed work. The task uses the work effort tied to other tasks to drive its performance. Use this method for discrete work that is related to other discrete work. Use this method if your organization uses earned value management methodology for measuring project performance and has projects and tasks that use this method. When you use this method, you enter the BCWP at the task level. Use the BCWP Override field in the Earned Value section of the task properties page.

More information:

How to Work with Project Management Settings

How to Set Up Projects for Tracking Costs

Set the Default Earned Value Options (Tasks)

Create New Baselines (Investments)

How to Calculate and Record Earned Value Totals

Set the Default Earned Value Calculation Method

You can define the default method in which earned value is calculated for projects and project tasks. The default setting for the earned value calculation method for projects and tasks is percent complete. If your organization uses earned value management methodology for measuring project performance, you can set the default earned value calculation method to that methodology. Edit the Project and Task objects in Studio to set the EV Calculation Method attribute.

Note: If you are using CA Clarity PPM with Microsoft Project and you specify an earned value calculation method other than percent complete, use CA Clarity PPM to calculate, display, and report earned value metrics.

For more information, see the Studio Developer’s Guide.

More information:

Programs

How to Work with Project Management Settings

About Earned Value Calculation Methods

Set the Default Resource Booking Options

Mixed booking lets hard and soft allocations for resources on projects. To allow resources with separate hard and soft allocations, select the system setting for Allow Mixed Booking on the settings page.

Follow these steps:

  1. Open Administration, and from Project Management, click Settings.

    The settings page appears.

  2. Complete the following field:
    Allow Mixed Booking

    Defines to let project managers edit the allocation of hard-booked resources, to mix booked resources on projects. Also, to extend a resource to do additional project planning.

    Default: Selected

    Note: If a mixed booking exists on the project, the field is read-only.

  3. Save the changes.

More information:

Accept Hard Allocation

About Booking Already-Booked Resources (Investments)

About Base Calendars

Base calendars are templates that you can use to create individual resource calendars. Resource calendars are used to perform important calculations involving resource availability, such as capacity as opposed to demand, or over-allocated resources.

Most often the standard calendar is used. But, you can change the characteristics of the base calendar to suit your needs. For example, you can change the workdays and nonworkdays of the week. You can set up to four standard shifts.

You cannot delete the standard calendars, or base calendars that have child calendars. In which case, before you delete the parent calendar, delete the child calendars.

More information:

Create New Calendars

About the Default Shift (Base Calendar)

Define Days as Workdays (Calendars)

Set Resource Shifts (Calendars)

Reset Base Calendar Shifts

Change Base Calendar Parent/Child Relationships

Create New Calendars

Use the following procedure to create a custom calendar. A custom calendar can be created based upon an existing calendar. The latter is the parent calendar.

Follow these steps:

  1. Open Administration, and from Project Management, click Base Calendars.

    The base calendars page appears.

  2. Click New.

    The edit calendar properties page appears.

  3. Complete the following fields, and then click Add:
    Calendar Name

    Defines the new calendar name.

    Base Calendar

    Specifies the calendar to base this calendar. The base calendar is the parent to the new calendar.

    Example: Standard

    Standard

    Specifies the calendar as the standard calendar in CA Clarity PPM.

    Default: Cleared

  4. Save the changes.

About the Default Shift (Base Calendar)

The default shift for the base calendar is eight hours per day. You can set new shifts to override the default shift. When you change a specific holiday on the resources calendar to a nonworkday, the shift information or availability is removed. If you change the day back to a workday, a check is made to see if a shift pattern exists for that day in that calendar (or parent). One of the following actions occurs:

Define Days as Workdays (Calendars)

You can select days as workdays or as non-workdays. To select dates by days of the week, select the check box next to the day of the week and click Make Workday. To change dates from workdays to non-workdays, select the check box next to each date. Then, click Make Non-Workday.

Follow these steps:

  1. Click Base Calendars and click the name of the calendar.

    The edit calendar exceptions page appears.

  2. Select the month at the top of the calendar to edit.

    The month displays on the edit base calendars page.

  3. Indicate which days are standard workdays. Select the check box next to each date and then click Make Workday.

    The changes are saved.

Set Resource Shifts (Calendars)

Follow these steps:

  1. Click Base Calendars and click the name of the calendar.

    The edit calendar exceptions page appears.

  2. Select the month at the top of the calendar to edit.

    The month displays.

  3. Select the check box next to the days having the same shift, and click Set Shifts.

    The shifts page appears.

  4. Enter the starting and ending hour for up to four shifts
  5. Save your changes.

Reset Base Calendar Shifts

When you reset the shift by resetting a base calendar, the base calendar shift information is picked up for that day. This information is important when you use a shift other than eight hours, and can affect resource availability and allocation.

Follow these steps:

  1. Click Base Calendars and click the name of the calendar.

    The edit calendar exceptions page appears.

  2. Select the check box next to each date to reset, and then click Reset to Base.

    The shift is reset to the base calendar.

Change Base Calendar Parent/Child Relationships

To delete a parent calendar or change to another parent, use the following procedure to change that relationship.

Follow these steps:

  1. Click Base Calendars and click the name of the calendar.

    The edit calendar exceptions page appears.

  2. Click Edit Calendar Properties.

    The edit calendar properties page appears.

  3. Complete the following field:
    Base Calendar

    Specifies the calendar to base this calendar. The base calendar is the parent to the new calendar.

    Example: Standard

  4. Save the changes.

Risk Category Types

Add risk categories to group investment risks by a particular type. You can add additional risk categories, and then add these categories to object attributes, such as the Category Type lookup attribute. The lookup attribute defines the predefined risk category or factors that the resources can view when defining the detailed project and overall risks.

For more information, see the Administration Guide.

More information:

How to Add New Risk Categories

How to Add New Risk Categories

Your CA Clarity PPM administrator can add new risk categories/factors. The risk categories display in the Contributing Factors section of the main risk page. The project Risk field displays a weighted average of all risk categories or factors displayed on the page.

Use the following process to add new risk categories:

  1. Create a number attribute (field) for the project object Properties view, to the Contributing Factors section of the Risk subpage view. The new number attribute is a formula field calculated based on a weighted average formula.
  2. Publish the view. Publish the view for the new risk category to display on the page. The users can then enter values for the risk category.

For more information, see the Studio Developer’s Guide.

About the Risk Score Matrix

Use the Risk Score matrix to determine the degree of risk (low, medium, or high) based on the risk impact and probability factors. The risk probability values are plotted against the risk impact values. The intersection of every probability and impact value is the risk score.

More information:

Set Risk Threshold

Set Risk Threshold

Use the following procedure to set the system-level default project risk score and overall risk threshold. The risk threshold is the acceptable level of risk that can be tolerated without acting out the risk response strategy. You can also set the probability and impact values for the projects that have detailed risks.

You can change the existing risk thresholds, which help to calculate the degree of risk. But the changes are not based on the changes to the risk score matrix.

Follow these steps:

  1. Open Administration, and from Project Management, click Risk Settings.

    The risk settings page appears.

  2. Complete the following field:
    Risk Threshold

    Defines the risk acceptance level for all projects.

    Default: 4

  3. Set the risk score for a given impact and probability combination
  4. Save the changes.

Earned Value Reporting Periods

The earned value reporting period defines the frequency and the interval for the Update Earned Value History job. The job takes historical earned value snapshots of performance and saves them in the earned value history table. When using earned value methodologies to analyze project performance, the job uses the earned value reporting period to take the snapshot. It saves the snapshot based on the project association to the period. The project manager associates the project to the appropriate period.

By setting up reporting periods, you define the time intervals used to save earned value (EV) information, such as weekly or monthly. The periods store and calculate historical earned value.

You can delete earned value reporting periods from the list page.

More information:

Create Earned Value Reporting Periods

Edit Earned Value Reporting Periods

How to Set Up Timesheets

About Input Type Codes

About Invalid Transactions

How to Work with Project Management Settings

About Base Calendars

Risk Category Types

About the Risk Score Matrix

Earned Value Periods

Create Earned Value Reporting Periods

Create the earned value reporting periods used by project managers for earned value analysis (EVA). When you define the reporting period, you define how often the report runs.

Project managers associate their projects to defined reporting periods. Historical earned value snapshots of project performance are taken based on this reporting period.

Weekly Frequency Example

For a weekly recurrence of the reporting period, enter 1 as the frequency. For a recurrence to happen every other week, enter 2. For twice a year, enter 26. And once a year, enter 52.

Follow these steps:

  1. Open Administration, and from Earned Value Management, click Period Definitions.

    The list page appears.

  2. Click New.

    The create page appears.

  3. Complete the following general fields:
    Name

    Defines the name for the earned value reporting period.

    Limits: 80

    Required: Yes

    ID

    Defines the unique identifier for the earned value reporting period.

    Limits: 16

    Required: Yes

    Description

    Defines the reporting period description.

    Active

    Indicates if this reporting period is active. When the reporting period is active, project managers can associate projects to it.

    Default: Selected

    Period Type

    Defines the period type. Once you select a period type, define the recurrence of the selected period.

    Values:

    Weekly, Monthly, Quarterly, Annually

  4. Save the changes.

Edit Earned Value Reporting Periods

Follow these steps:

  1. Open the earned value reporting period.

    The earned value reporting period properties page appears.

  2. Edit the following fields:
    Name

    Defines the name for the earned value reporting period.

    Limits: 80

    Required: Yes

    ID

    Defines the unique identifier for the earned value reporting period.

    Limits: 16

    Required: Yes

    Description

    Defines the reporting period description.

    Active

    Indicates if this reporting period is active. When the reporting period is active, project managers can associate projects to it.

    Default: Selected

    Period Type

    Defines the period type. Once you select a period type, define the recurrence of the selected period.

    Values:

    Weekly, Monthly, Quarterly, Annually

  3. Save the changes.

Earned Value Periods

The earned value (EV) periods are the buckets to which the earned value reporting period information goes. The Update Earned Value History job creates the periods as it needs them.

You can only delete consecutive ending time EV periods. Use the EV periods list page to delete EV periods.

More information:

Generate Earned Value Periods

Generate Earned Value Periods

Earned value (EV) periods are created automatically when the Update Earned Value History job runs. Or, using this procedure, create the earned value periods manually.

Follow these steps:

  1. Open Administration, and from Earned Value Management, click Period Definitions.

    The list page appears.

  2. Click the Calendar icon next to the earned value reporting period to generate a new EV period.

    The EV periods list page appears.

  3. Click Create.

    The generate EV periods page appears.

  4. Complete the following field:
    Number of New Periods

    Defines the number of new periods.

  5. Save the changes.