The following table maps fields from Microsoft Project to the CA Clarity PPM base calendar fields.
Note: The project calendar in Microsoft Project is always reset to the base calendar in CA Clarity PPM.
Microsoft Project |
CA Clarity PPM |
Notes |
---|---|---|
For |
Calendar Name PRCalendar: PRNAME |
Not used for resource calendars. |
Base Calendar |
Base Calendar PRCalendar: PRBASECALENDARID |
In Microsoft Project, only resource calendars have base calendars. Combines system calendars with their base calendars when this information is set in Microsoft Project. |
Set Working Time for Selected Dates |
PRCalendar: PRVALUE |
Calendar information defined in CA Clarity PPM is shown in the Set Working Time options in Microsoft Project. |
Copyright © 2013 CA.
All rights reserved.
|
|