Calendar Field Mapping (Microsoft Project)

The following table maps fields from Microsoft Project to the CA Clarity PPM base calendar fields.

Note: The project calendar in Microsoft Project is always reset to the base calendar in CA Clarity PPM.

Microsoft Project

CA Clarity PPM

Notes

For

Calendar Name

PRCalendar: PRNAME

Not used for resource calendars.

Base Calendar

Base Calendar

PRCalendar: PRBASECALENDARID

In Microsoft Project, only resource calendars have base calendars.

Combines system calendars with their base calendars when this information is set in Microsoft Project.

Set Working Time for Selected Dates

PRCalendar: PRVALUE

Calendar information defined in CA Clarity PPM is shown in the Set Working Time options in Microsoft Project.

More information:

About Base Calendars