About Base Calendars

Base calendars are templates that you can use to create individual resource calendars. Resource calendars are used to perform important calculations involving resource availability, such as capacity as opposed to demand, or over-allocated resources.

Most often the standard calendar is used. But, you can change the characteristics of the base calendar to suit your needs. For example, you can change the workdays and nonworkdays of the week. You can set up to four standard shifts.

You cannot delete the standard calendars, or base calendars that have child calendars. In which case, before you delete the parent calendar, delete the child calendars.

More information:

Create New Calendars

About the Default Shift (Base Calendar)

Define Days as Workdays (Calendars)

Set Resource Shifts (Calendars)

Reset Base Calendar Shifts