Delete a Scheduled Report Run

You can delete scheduled runs with a "Cancelled" or "Completed" status. Deleting a scheduled run does not delete the report type, or any completed generated reports listed in the Reports Library.

Follow these steps:

  1. Open Home, and from Personal, click Reports and Jobs.

    The list page appears.

  2. Open the Reports menu, and click Scheduled Reports.

    The scheduled reports page appears.

  3. Select the check box next to the run, and click Delete Job.