Release a Resource

Renewable resource dependencies can be defined using the Free attribute with one of the following options:

If you assign a resource as a dependency to a job with the attribute Free=N, and that job is terminated, the resource continues to be held by that job. For this resource to be available to other dependent jobs waiting to run, you must use the RELEASE_RESOURCE Send Event command to free the resource.

Note: The Free attribute is only valid for renewable resource dependencies.

To release a resource, do one of the following:

The resources for the selected job are released.

More information:

Job Resource Dependencies Flow

Job Resource Dependencies Report

Job Pop-Up Menu