The following table maps fields from Microsoft Project to fields on the task properties page in CA Clarity PPM:
Microsoft Project |
CA Clarity PPM |
Notes |
---|---|---|
General tab |
||
Name |
Name PRTask: PRNAME |
When saving the project to CA Clarity PPM, if the Name field is blank in Microsoft Project, it is set to the CA Clarity PPM internal ID. This field cannot be blank. |
Text1 |
ID PRTask: PREXTERNALID |
Task ID in the same project must be unique in CA Clarity PPM (except blank). |
Start |
Start PRTask: PRSTART |
The same calendar information is reflected in the Set Working Time in Microsoft Project. |
Finish |
Finish PRTask: PRFINISH |
The same calendar information reflected in the Set Working Time options in the Change Working Time dialog. |
Duration |
Duration This field is not displayed by default. PRTask: PRDURATION |
In Microsoft Project, you can set the duration unit in the Duration is entered in field on the Options dialog (Tools, Options). Elapsed durations are converted to their equivalent in work time duration, but the model is changed. |
Priority |
Priority This field is not displayed by default. PRTask: PRPRIORITY |
Priorities are translated between the range (0-1000) in Microsoft Project and the range (36-0) in CA Clarity PPM. Precision is lost. |
Flag1 |
Key Task PRTask: PRISKEY |
This is the default mapping, which you can change. |
Text5 |
Charge Code PRTask: PRCHARGECODEID |
The ID (PREXTERNALID) for the charge code is shown in Microsoft Project. To modify the charge code for a task, enter any existing CA Clarity PPM charge code ID. This mapping is the default mapping, which you can change. |
% Complete |
% Complete PRTask: PRSTATUS and PRTask: PRPCTCOMPLETE |
The task status is set to "Started" when the percent complete is greater than zero, or to "Complete" when it is 100. Otherwise, this field is set to "Not Started". |
Advanced tab |
||
Mark Task as Milestone |
Milestone PRTask: PRISMILESTONE |
In Microsoft Project, any task can be flagged a milestone as a means to drive Gantt bar rules. For example, drawing the diamond and other features such as filtering. Microsoft Project automatically sets this flag when a task acquires zero duration. |
Calendar |
|
You can use them in Microsoft Project, but the list of available calendars comes from CA Clarity PPM. |
Task Type |
Fixed Duration PRTask: PRISFIXED |
All types in Microsoft Project are supported. In Microsoft Project:
|
Effort Driven |
No Mapping |
Tasks flagged as Effort Driven in Microsoft Project take more processing. If there are many tasks, system memory requirements and performance can degrade noticeably. |
Constraints The constraints defined in Microsoft Project are stored in CA Clarity PPM, but you cannot edit them from Schedule Connect. Microsoft Project automatically sets the Start No Earlier Than constraint to hold a task start date. If you add a Start No Earlier Than constraint and Microsoft Project then adds a later Start No Earlier Than constraint to hold a task start date, the saved Start No Earlier Than constraint is not set. |
||
Constraint Type |
No CA Clarity PPM user interface field available PRConstraint: PRTYPE |
When opening the project in Microsoft Project, if multiple constraints in CA Clarity PPM exist for a task, the first constraint encountered is processed. |
Constraint Date |
No CA Clarity PPM user interface field available PRConstraint: PRTIME |
|