Managing Tasks › Task Relationships and Dependencies › Finish-Start Dependency Links › Create Finish-Start Dependency Chains
Create Finish-Start Dependency Chains
Use the following procedure to create a finish-start dependency chain between two tasks.
To create a finish-start dependency chain
- Open the project containing the task for which you want to create a dependency relationship.
The Project: Properties: Main - General page appears.
- Select the Tasks tab.
The Project: Tasks: Task List page appears.
- Select the Work Breakdown Structure subtab.
The Project: Tasks: Work Breakdown Structure page appears.
- Select the check boxes next to the tasks which will form a finish-start dependency chain, and click Link.
A link is created between the two tasks.
More information:
Display Task Relationships and Dependencies
Autoschedule