Create Finish-Start Dependency Chains

Use the following procedure to create a finish-start dependency chain between two tasks.

To create a finish-start dependency chain

  1. Open the project containing the task for which you want to create a dependency relationship.

    The Project: Properties: Main - General page appears.

  2. Select the Tasks tab.

    The Project: Tasks: Task List page appears.

  3. Select the Work Breakdown Structure subtab.

    The Project: Tasks: Work Breakdown Structure page appears.

  4. Select the check boxes next to the tasks which will form a finish-start dependency chain, and click Link.

    A link is created between the two tasks.

More information:

Display Task Relationships and Dependencies

Autoschedule