You can view a Gantt chart that displays your Plan of Record (POR) project data or tentative schedule data that was created when you autoscheduled your project. This Gantt chart also displays graphical dependencies between all tasks in your project. The chart includes data from master and subprojects based on the current project's work breakdown structure (WBS). You can only open one Gantt chart at a time.
The following columns are displayed on the left pane:
Displays the task's name.
Displays the task's unique identifier.
Displays the task's start date.
Displays the task's finish date.
Displays the variation from the finish date, based on the following formula:
Finish Variance = Finish - Baseline Finish
Displays the task's estimated time for completion in hours.
Values:
Total Effort = ETC + Actuals
To display all task relationships and dependencies for a project
The Project: Properties: Main - General page appear.
The Project: Tasks: Task List page appears.
A Gantt chart appears displaying task dependencies and relationships for the current project.