Autoschedule is an automated way for you to create project schedules. Autoschedule schedules tasks based on an internal set of rules that are set by the system. Each task is scheduled:
Autoschedule automatically schedules tasks based on task dependencies, constraints, priority order, and related date and resource logic. Autoscheduling allows you to model your plan and generate dates for your tasks and your overall project. Before publishing a schedule as a plan of record, you are able to see the results of scheduling and make any adjustments. By default, Autoschedule is designed to eliminate or minimize resource overallocation.
Autoschedule uses task duration and task date constraint and dependency information to identify the project's critical path—the best way to schedule project tasks while minimizing the delays and expansions that can cause deadline slippage, and at the same time, minimizing resource overallocation. The critical path determines the earliest finish date of the project.
Autoschedule uses critical path data to make the following scheduling adjustments:
| Copyright © 2010 CA. All rights reserved. | Email CA Technologies about this topic |