You can draw down the budget from your SLPP into a control account's work package. Do this once the time comes to do the future work but prior to starting the work.
Drawing down the budget is not an automated process. You must manually draw a portion of it or the entire amount of the SLPP's budget down to the work package. Use the following process to draw down your SLPPs and transfer the budget into a planning work package: