Summary Level Planning Packages (SLPP)

This section contains the following topics:

Create SLPPs

View Summary Level Planning Packages (SLPP) Remaining Budget

How to Draw Down SLPP Budget into Work Packages

Delete Summary Level Planning Packages (SLPP)

Create SLPPs

You can create SLPPs from the CWBS Element: Summary Planning Packages list page. Create them at the lowest level of the CWBS hierarchy. Do this so that when the time comes to do the future work and you draw down the SLPP budget into a control account's work package, the SLPP is at the same level as the control account.

To create a SLPP

  1. Open the contract.

    The Contract: Properties page appears.

  2. Click the Contract WBS tab.

    The Contract: Contract WBS page appears.

  3. Expand the CWBS hierarchy to locate the CWBS element for the new SLPP, and click the name of the CWBS element.

    The CWBS Element: Properties page appears.

  4. Click the Summary Planning Packages tab.

    The CWBS Element: Summary Planning Packages list page appears.

  5. Click New.

    The Create Summary Planning Packages page appears.

  6. Complete the following fields:
    Summary Planning Package Name

    Required. Defines the SLPP's name.

    Summary Planning Package ID

    Required. Defines the SLPP's unique identifier.

    Budget

    Defines the SLPP's assigned budgeted amount. When you take a contract baseline, this value is used for the SLPP Budget At Completion (BAC).

    Description

    Defines the SLPP's description.

    Start

    Required. Defines the SLPP's start date.

    Finish

    Required. Defines the SLPP's finish date.

    OBS

    Defines the SLPP's OBS Unit. This value is used for aggregation of earned value metrics and baseline data on the CPR Format 2 report.

  7. Click Submit.

    The SLPP is created and displays on the CWBS Element: Summary Planning Packages list page.

More information:

Contract Performance Report (CPR) Format 2 - Organizational Categories

How to Draw Down SLPP Budget into Work Packages