This section contains the following topics:
View Summary Level Planning Packages (SLPP) Remaining Budget
How to Draw Down SLPP Budget into Work Packages
Delete Summary Level Planning Packages (SLPP)
You can create SLPPs from the CWBS Element: Summary Planning Packages list page. Create them at the lowest level of the CWBS hierarchy. Do this so that when the time comes to do the future work and you draw down the SLPP budget into a control account's work package, the SLPP is at the same level as the control account.
To create a SLPP
The Contract: Properties page appears.
The Contract: Contract WBS page appears.
The CWBS Element: Properties page appears.
The CWBS Element: Summary Planning Packages list page appears.
The Create Summary Planning Packages page appears.
Required. Defines the SLPP's name.
Required. Defines the SLPP's unique identifier.
Defines the SLPP's assigned budgeted amount. When you take a contract baseline, this value is used for the SLPP Budget At Completion (BAC).
Defines the SLPP's description.
Required. Defines the SLPP's start date.
Required. Defines the SLPP's finish date.
Defines the SLPP's OBS Unit. This value is used for aggregation of earned value metrics and baseline data on the CPR Format 2 report.
The SLPP is created and displays on the CWBS Element: Summary Planning Packages list page.