Once you have entered the budget amount you want to draw down from the SLPP into the work package, you must manually reduce the SLPP budget by the amount you entered in the work package. Use the Summary Planning Package: Properties page's Budget field to report the amount.
To manually reduce an SLPP's budget
The Contract: Properties page appears.
The Contract: Contract WBS page appears.
The CWBS Element: Properties page appears.
The CWBS Element: Summary Planning Packages list page appears.
The Summary Planning Package: Properties page appears.
The SLPP's budget is reduced by the amount you are drawing down.