Manually Enter Work Package Budget Amount Drawn Down from SLPP

You can manually enter the budget amount for those planning work packages that you are drawing down from the summary level planning package (SLPP). Enter this amount on the Work Package: Properties page.

To manually enter a planning work package's budget amount

  1. Open the contract.

    The Contract: Properties page appears.

  2. Click the Contract WBS tab.

    The Contract: Contract WBS page appears.

  3. Click the name of the CWBS element.

    The CWBS Element: Properties page appears.

  4. Click the Control Accounts tab.

    The CWBS Element: Control Accounts page appears.

  5. Click the name of the control account.

    The Control Account: Properties page appears.

  6. Click the Work Packages tab.

    The Control Account: Work Packages list page appears.

  7. Click the name of the planning work package you want to edit.

    The Work Package: Properties page appears.

  8. In the Earned Value Management section, enter the budget amount in the Budget (BAC) field, and click Submit.

    Your changes are saved.