Create user stories and issues with tasks in CA Clarity™ Agile and assign them to sprints and releases (product, master, or both). Corresponding tasks are automatically created in the linked CA Clarity™ PPM project. Only user stories that are assigned to the master release display in the work breakdown structure if the CA Clarity™ PPM project is linked to a master release in CA Clarity™ Agile. All products that are associated to the master release appear at the top level.
The work breakdown structure of the CA Clarity™ PPM project tasks is built as follows:
If the CA Clarity™ PPM project is linking to a master release in CA Clarity™ Agile, the WBS hierarchy looks like the following:
Product – Release
Sprint
User Story
Task
Product – Release
Kanban Board
User Story
Task
If the CA Clarity™ PPM project is linking to a product release in CA Clarity™ Agile, the WBS hierarchy looks like the following:
Sprint
User Story
Task
Kanban Board
User Story
Task
|