When you enter the hours worked on a task in CA Clarity™ Agile using the Task Worklog or the Virtual Wall, the following updates occur in CA Clarity™ PPM:
The following table shows how CA Clarity™ Agile task worklog information maps to CA Clarity™ PPM timesheets:
|
CA Clarity™ Agile Worklog |
CA Clarity™ PPM Timesheet |
|---|---|
|
Agile User Name/Assigned To |
Resource Name |
|
Hours Worked |
Hours logged for one day |
|
Hours Remaining |
ETC |
|
Work Date |
A day in the timesheet time period |
|
Task Type |
Charge Code |
Each time you update your worklog in CA Clarity™ Agile, the corresponding timesheet is updated in CA Clarity™ PPM as long as the timesheet is not in submitted status.
You can delete your worklog in CA Clarity™ Agile even if time has already been populated in a CA Clarity™ PPM timesheet. If the timesheet is currently not submitted, it is updated based on the latest updates from CA Clarity™ Agile. If the timesheet is already submitted, create a timesheet adjustment.
|