Propagate Dueout Times

You can propagate dueout times if you want an early warning that jobs in the Application are running late.

Follow these steps:

  1. Open the Application in the Define perspective.

    The Application appears in the workspace.

  2. Right-click the Application in the Application Workspace view, and select Properties from the pop-up menu.

    The Basic page of the Application properties dialog opens.

  3. Select the Propagate dueout time check box and click OK.

    The server enables anticipated end times and critical path analysis and propagates dueout times in the Application.

Note: If you want this option to apply to all Applications that you define, from the main menu click Window, Preferences, Desktop Client, Define Perspective, Application defaults, and select the Propagate dueout times check box.