If the Estimate end time or Propagate dueout time option is enabled in the Application properties, the server calculates the anticipated end times for all jobs in the Application when it generates the Application. The server recalculates anticipated end times every time the state of a job changes in the Application. You can review the Application, at any stage, and determine when any job is expected to complete.
The server calculates the anticipated end times of jobs based on Event submission time, predecessor dependencies, time dependencies, and the job's average execution time. You can override the average execution time the server uses to calculate a job's anticipated end time when you define the job or modify the job definition.
Note: If a job does not have an average execution time when it runs, the server does not calculate the anticipated end time of the job. In future runs, the server calculates the anticipated end time of the job based on the historical execution times of the job.
|