LRDY LRDY,JOB=G401
LRDY LIST= DATE=YY.DDD PAGE 0001 JOB QUEUE CA-7 -DAY(DDD) AND TIME(HHMM)-- CPU SCH ENTRY MSTR JOB NAME NAME NUM DEADLINE SUB/START DUE-OUT SPEC/RUN ID MODE REQ STATUS PERAC01D RDY 0016 084/1649 084/1549 084/1649 SY2- 001 DEMD 000 LATE WHSAA01D RDY 0019 084/1730 *NONE* 084/1800 ALL- 005 AUTO 000 RUSH SLIF-00 REQUEST COMPLETED AT 16:57:15 on YY.DDD
This panel contains the following fields:
Indicates the name of the job as defined in the database. See NAME field on the job definition panel.
RDY indicates that only the ready queue is listed.
Indicates the CA Workload Automation SE assigned job number.
Indicates a calculated time by which this job should be active on the CPU to be completed by the due-out time.
Indicates the time that the job was written either to a submit data set or to the internal reader if there is a date and time value here. A value of *NONE* denotes that this job has not yet been submitted.
Indicates the due-out time for the job.
Indicates two values. The SPEC value is what CPU this job should be submitted to (see MAINID field on DB.1 panel). The RUN value is the system where it ran.
For XPJOB jobs this field displays XPJ for SPEC. When the job begins execution, the RUN field displays 7XPJ.
For agent jobs, this field displays the agent job type for SPEC. When the job begins execution, the RUN field displays AGJ.
Indicates the schedule ID assigned when this job was brought into the request queue.
Indicates how the job was brought into the queue. Values are the following:
ARF recovery job.
Indicates triggered job.
Demanded job.
Job submitted external to CA Workload Automation SE.
Job record to be loaded (brought in by the LOAD command).
Job submitted by Personal Scheduling System.
Repeated job.
Job brought in by the RUN command.
Job record brought in by schedule scan.
Job brought in by the DEMAND command from an XPS client.
Job brought in from an XPS client using the RUN command with the REF option.
Job brought in from an XPS client using the RUN command.
Note: If ARF detects an exception condition for the job, the last character of this field has an asterisk as in the following: DEM*
Indicates the master requirement count. This field is zero for a job in the ready queue.
Indicates a condition on this job record. Possible values are the following:
Indicates the job has not started by the DEADLINE DAY/TIME.
If the job is in the ready queue with this status, then a job purge record was received before a job initiation record.
Indicates the RUSH command was entered for this job.
Copyright © 2013 CA Technologies.