Previous Topic: Process Metric Statistics Data RecordNext Topic: Step 1: Create a CSV file


How You Graph Seven or More CPUs

Performance Manager can graph six CPUs per command. If you need to create a graph that displays seven or more CPUs for a node, you need to write CSV files for 6 CPUs at a time, manually create a merged CSV file, move the file to a Windows® machine, and then use Microsoft Excel® to create a graph.

To graph seven or more CPU's complete the following tasks in order:

  1. Create a CSV file
  2. Create More CSV Files as Necessary
  3. Create a Single CSV File
  4. Send the CSV file to a Windows Machine
  5. Create the graph in Excel

This section contains the following topics:

Step 1: Create a CSV file

Step 2: Create More CSV Files as Necessary

Step 3: Create a Single CSV File

Step 4: Send the CSV File to a Windows Machine

Step 5: Create the Graph in Excel