There are two ways to change the Move Request QA Move Date, Prod Move Date, and the First Run Date:
The Change function can be used to update any user‑entered Move Request data for Move Requests in the statuses of Being Created, Awaiting QA Approval, or Awaiting Prod Approval. The Change function revokes any approvals that are granted before the Move Request is completely approved. This function also deletes all approval comments.
The Date Change function can be used at any time in the Move Request Life Cycle regardless of the current status of a Move Request. Normally, the Date Change function is limited to System Administrators or to members of a limited group. As distributed, only Administrators and users with the Operations attribute can use the DAT function.
Select the Date Change function from the Move Request Maintenance panel, APIP100. Type DAT in the Action field, enter the number of your Move Request in the Move Req field, and press ENTER.
You can also type DAT in the Action field of the Browse Move Requests List panel, APIP231.
The Move Request Date Change panel, APIP220, displays. This panel is used to update the Move Dates or the First Run Date regardless of the Move Request status. You can display Approval Category descriptions by entering the AC command.
|