Example: REPORT Command

The next REPORT command to be issued after a REPORT CLOSE command creates a new report data set.

REPORT STATES AT 1300 ON 2/21/2005

The following would be the contents of data set JOEUSER.SM.OPS44R.PRODUCTI.D0030415.T1509. Note that this report is for the identical point in time that is shown in the example SHOW STATES display in Viewing Potential State Changes in this chapter.

Schedule: OPS44R>PRODUCTION ----------- STATES ----------- 15 Apr 2007 ------------------------- AT 1300 ON 02/21/2005 (MON) ----------------- Table: ACF2_STCTBL Type: *NULL* ACF2 ON WEEKDAY .MTWTF. 0800-1600 Table: CICS_STCTBL Type: *NULL* CICS ON WEEKDAY .MTWTF. 0800-1600 CICSTEST OFF WEEKDAY .MTWTF. 0800-1600 Table: IMS_STCTBL Type: *NULL* IMS ON WEEKDAY .MTWTF. 0800-1600 Table: JES2_STCTBL Type: *NULL* JES2 ON WEEKDAY .MTWTF. 0800-1600 Table: TSO_STCTBL Type: *NULL* TCAS ON WEEKDAY .MTWTF. 0800-1600 TCASTEST OFF WEEKDAY .MTWTF. 0800-1600

The REPORT LINKS command generates a report identical to that of a REPORT call to the Schedule Manager API. The next section describes the API in general and the REPORT call, and also includes a sample report.