Copy a Schedule

The two ways to create a copy of a schedule are:

To create a copy of a schedule from the Primary Panel

  1. Type the name of the schedule to be copied into the NAME field.
  2. Type the name to assign to the copy in the NEWNAME field.
  3. At the command line, type C and press Enter.
  4. Press Enter again to confirm that you want to copy the schedule.

To create a copy of a schedule from the Schedule List Panel

  1. Type a C in the SEL column next to the name of the schedule you want to copy.
  2. Type the name of the target schedule in the New Schedule field on the same line.
  3. Press Enter, and then Enter again to confirm that you want to copy that schedule.

Result-The Schedule Manager creates an exact duplicate of the named schedule and gives the copy the name specified in the NEWNAME/New Schedule field. The duplicate schedule contains the same periods and links to the same resources as the original schedule.