The Dependency tab lets you specify the factors based on which the job should execute at the scheduled time.
This tab contains the following fields:
Runs the job only if the status of the given job is OK. This option is useful when the job to be carried out is dependent upon the successful completion of another job. You can select the latter from the list box, which lists all the jobs defined in the domain.
Example: Assume that you are doing a software distribution job in stages as described here:
If stage 1 fails, or if the user says No when prompted, stages 2 and 3 should not be executed.
Runs the job only on completion of the job on a related asset. This works in the following way:
Lets you select the following file dependency factors, when selected:
Executes an action depending on the existence of the selected file. You can select the file by typing the path and file name or by browsing in the File Text Field and Browse Button fields.
Executes an action depending on the non-existence of the selected file. Enter the name of the non-existing file in the File text field.
Defines the file name and path on which the job is dependent. You can either enter or browse for the existing file. Clicking the Browse button opens the Select File dialog.
Note: Browsing is done on the manager, but the file you want to select as a dependency must exist on the agent system. If the file does not exist on the manager, you must enter the file path name instead of browsing for it.
Specifies the maximum number of simultaneous executions of an action per Scalability Server. If the agent belongs to a large Scalability Server and all other agents must be updated, set a maximum number of simultaneous executions, to distribute the network load over a period.
|