Previous Topic: Update Idea PropertiesNext Topic: Define Budget Information


Define Scheduling Information

Use this procedure to define the idea start and finish dates, open the idea for time entry, and define its charge code.

Follow these steps:

  1. Open Home, and from Demand Management, click Ideas.
  2. Open an idea.
  3. Click the Properties tab and click Schedule.
  4. In the Schedule section of the page, complete the following fields:
    Start Date

    Indicates the idea start date. When you convert the idea into an investment, the date is the investment start date.

    Finish Date

    Indicates the idea finish date. When you convert the idea into an investment, the date becomes the investment finish date.

    Set Planned Cost Dates

    Specifies if the planned cost dates are synchronized with the investment dates. Selecting the option for a detailed financial plan does not affect the planned cost dates.

    Default: Selected

  5. In the Tracking section of the page, complete the following fields:
    Time Entry

    Select the field to allow staff members to record the time they work on the idea on the timesheets.

    Important! Ensure that you select the Time Entry field to enable staff members to record work on ideas on the timesheets.

    Default: Selected

    Track Mode

    Indicates the method for the staff members to enter time for hours worked on the idea.

    Options:

    • Clarity. Staff members record time using timesheets.
    • None. Non-labor resources track actuals through transaction vouchers or through a scheduler, such as Open Workbench.
    • Other. Import actuals from a third-party application.

    Default: Clarity

    Charge Code

    Select a default charge code to use for all idea tasks. If you enter a different charge code at the task level on timesheets, the task-level charge codes override the idea-level charge code.

  6. Click Save and Return, or Submit for Approval.