Previous Topic: Define Scheduling InformationNext Topic: Financial Plans for Ideas


Define Budget Information

To evaluate ideas for portfolio management, define the planned cost and benefit information for each idea. You can define budget information from the Idea: Properties: Main - Budget page. With budget properties, you can define metrics. For example, the idea planned cost, NPV, ROI, and breakeven information. You can also elect to have the application calculate budget metrics for you automatically using the cost of capital.

Use the fields on the page to set the start and end dates for the budget. With budget properties, money flows constantly and evenly over this period. The values budget properties are applied to only one time period: from the idea start date to the finish date. The dates are applied only to your idea and not to its parent investments.

Follow these steps:

  1. Open the idea and click its subject.
  2. Open the Properties menu and then from Properties, click Financial Summary.
  3. Complete the following fields in the Financial Planning section:
    Currency

    Defines the currency for the investment.

    Default: System currency

    Budget equals Planned Values

    Specifies if the budget values in the budget properties of an investment match the planned values. If a detailed budget plan exists for the investment, all the field values in the Budget section are display-only. The fields reflect the values in the detailed budget plan. When the check box is cleared, you can edit the budget fields.

    Default: Selected

    Calculate Financial Metrics

    Specifies if financial metrics for the investment are calculated automatically. If unselected, you can define the financial metrics manually.

    Default: Selected

  4. Complete the following fields in the Financial Metrics Options section:
    Use System Rate for Total Cost of Capital

    Select the field to calculate the total cost of capital at system rate.

    Use System Reinvestment Rate

    Select the field to calculate the total cost of capital at the system reinvestment rate.

    System Rate

    Displays the system rate for calculating the total cost of capital.

    Investment Rate

    Displays the investment rate for calculating the total cost of capital.

    Initial Investment

    Defines the initial investment on the idea.

  5. Complete the following fields in the Planned section:
    Planned Cost

    Defines the idea planned costs. The value is distributed between the Planned Cost Start and the Planned Cost Finish dates.

    Note: When you convert the idea into an investment, the planned cost value supersedes the estimated cost entered in the Estimated Costs and Benefits section of the Idea Properties: General page.

    Planned Cost Start

    Select the date of starting the idea planned cost.

    Planned Cost Finish

    Select the date the idea planned cost expires.

    Planned Benefit

    Defines the total planned benefit you receive from the idea.

    Note: When you convert the idea into an investment, the planned benefit value supersedes the estimated benefit entered in the Estimated Costs and Benefits section of the Idea Properties: General page.

    Planned Benefit Start

    Select the date when the idea planned benefit starts.

    Planned Benefit Finish

    Select the date when the planned benefit of the idea expires.

    Planned NPV

    Displays the planned NPV (Net Present Value) of the investment.

    Planned ROI

    Displays the planned ROI (Return on Investment) of this investment.

    Planned Breakeven

    The date when the idea planned cost equals the planned benefit. The field is read-only.

    Planned IRR

    Displays the planned internal rate of return for the investment.

    Planned MIRR

    Displays the planned modified internal rate of return (MIRR) for the investment.

    Planned Payback Period

    Displays the date of the investment planned payback period.

  6. The following fields display in the Budget section.
    Budget Cost

    Displays the budgeted cost amount for the investment.

    Budget Cost Start

    Displays the budgeted cost start date of the investment.

    Budget Cost Finish

    Displays the budgeted cost finish date of the investment.

    Budget Benefit

    Displays the budgeted benefit amount of the investment.

    Budget Benefit Start

    Displays the budgeted benefit start date of the investment.

    Budget Benefit Finish

    Displays the budgeted benefit finish date of the investment.

    Budget NPV

    Displays the budgeted NPV (Net Present Value) of the investment.

    Budget ROI

    Displays the budgeted ROI (Return on Investment) of this investment.

    Budget Breakeven

    Displays the date when the idea budgeted cost equals the planned benefit. The field is read-only.

    Budget IRR

    Displays the budgeted internal rate of return for the investment.

    Budget MIRR

    Displays the budgeted modified internal rate of return (MIRR) for the investment.

    Budget Payback in Months

    Displays the date of the investment budgeted payback period.

  7. Submit your changes.
  8. View an Overview of Estimated Cost and Benefits.