Delete Baselines

Use the Multiple Baselines dialog to delete a baseline or to edit your baseline. If you want to delete a previous baseline but that baseline is marked as current, clear the Current field before deleting. You can only delete the current baseline if it is the only baseline listed.

Follow these steps:

  1. Open the Project ribbon.
  2. Click Manage in the Baselines group.
  3. Select the baseline row you want to delete, and click Delete.

More information:

Baseline Projects

Clear Baseline Values

Edit Baselines

Rebaseline Projects