Schedule Projects › Baseline Projects › Clear Baseline Values
Clear Baseline Values
Use the Set Baseline dialog to clear the baseline values or to rebaseline. Clearing baseline values replaces the existing baseline data that has been set for all of the tasks in a project, all of the tasks in the active view, or a selection of tasks. If you are using Open Workbench with CA Clarity PPM, save the project to CA Clarity PPM after you clear the current baseline values.
To delete entire baselines, use the Multiple Baselines dialog.
Follow these steps:
- Open the Project ribbon
- Click Define in the Baselines group.
- Select one of the following options in the Scope section:
- Project to clear the baseline of all the tasks in the current project.
- View to clear the baseline of the tasks in the active view.
- Selected Task(s) to clear the baseline of the selected tasks.
- Select Clear in the Baseline Settings section and click OK.
- Click Yes to accept the change when prompted with a warning that clearing the baseline replaces your existing baseline data.
More information:
Delete Baselines
Rebaseline Projects