Previous Topic: Define Autoschedule ParametersNext Topic: Autoschedule Projects from a Start Date


Autoscheduling Master Projects

You can autoschedule a group of subprojects from the master project to show the best fit of all tasks in all projects.

Best Practices: Before you autoschedule a master project, create a project start milestone for each subproject and link it to the first task in the master project. You can then lock or define a Start No Earlier Than date constraint to the milestone to assist with the individual project time frame constraints.

The master project's resource list contains the names of the resources assigned to work on the projects that are contained in the master projects, the subprojects.