Use the Autoschedule dialog to specify the scheduling criteria and to begin scheduling tasks using autoschedule. You can autoschedule an entire project or only tasks that occur between ranges of dates.
The following procedure explains how to define autoschedule parameters and to schedule your project.
Follow these steps:
Defines the date from which to begin scheduling tasks. To schedule from the finish date, enter the date on or before which you want to begin scheduling tasks.
Defines the date before which you want tasks to be excluded. For example, if you enter 4/3/2008 as the Ignore Tasks Starting Before date, and you have a task starting on 3/31/2008, this task is excluded from the schedule.
Defines the date after which you want tasks to be excluded. For example, if you enter 4/3/2008 as the Ignore Tasks Starting After date, and you have a task starting on 4/10/2008, this task is excluded from the schedule.
Specifies whether you want autoschedule to consider resource availability when scheduling the project.
Default: Selected
Note: If you clear this check box, autoschedule treats resources as having unlimited availability. Each task is scheduled against the resources total availability, not against the resources remaining availability which takes other task assignments into consideration. This results in the shortest possible schedule, but it may also cause resources to be overcommitted.
Specifies whether you want autoschedule to perform a backwards schedule from a defined deadline date.
Default: Cleared
Note: If you select this check box, the Start Date field toggles to the Finish Date field.
Specifies whether you want autoschedule to honor any constraints or dependencies you have on tasks with a status of Started.
Default: Cleared
Note: If you select this check box, you run the risk of overallocating resources or violating task dependencies.
Specifies whether you want autoschedule to move the assignment ETC within the scheduling Start Date and the task's Finish Date.
Default: Cleared
Specifies whether you want autoschedule to start successor tasks with zero lag the day after the predecessor task finishes. When cleared, successor tasks start the same day as the predecessor task finishes as long as the resource has availability left.
Default: Cleared
Note: This applies to variable-duration tasks only.
|
Copyright © 2014 CA.
All rights reserved.
|
|