Define Resource Maximum Percentage on Tasks

The following procedure explains how to define a resource's maximum percentage on a task.

Follow these steps:

  1. Open a view that displays the task detail pane.
  2. Right-click a task and click Assignments in the shortcut menu.
  3. Enter the maximum percentage amount in the Max % field in the Assigned Resources grid, and click OK.

    Note: If necessary, use the scroll bar to view this field.

More information:

Define the Resources Properties

Resource Loading Patterns