Tasks constitute the work steps of your project. During the project planning process, you define the tasks that are required to complete in order to accomplish the objectives of the project. In Open Workbench, the project tasks are organized according to a Work Breakdown Structure (WBS). The default WBS for Open Workbench includes the following hierarchical levels:
Note: You can change the labels that are used to identify your WBS levels.
Phases are the major steps that are required to achieve the project's goal. Most well-defined projects have multiple phases with specific objectives. Within each phase, there are a number of activities leading to the completion of the phase's objectives. You can further divide each activity into tasks and milestones. A task is the smallest identifiable project component. A milestone marks significant events or dates that are used to measure the progress of a project.
Only the memory and disk space on your computer limit the number of tasks you can add to a project or a WBS.
|