Use the following procedure to enter time-varying ETC segments at the resource assignment level.
Click Add to create a segment.
Follow these steps:
The list page appears.
The task assignments page appears.
The resource assignment properties page appears.
Specifies the loading pattern to distribute the ETC for a task assignment over the duration of the task. Auto-schedule schedules the work based on the loading pattern.
Values: Back, Uniform, Fixed, Contour, or Front
Default: Front
Select Fixed to enter the distribution of the work effort.
Specifies the start date for the time segment. Click the calendar icon and select a start date for the new time segment.
Specifies the finish date for the time segment. Click the calendar icon and select a start date for the new time segment.
Specifies the number of ETC hours for the time segment.