Use the following procedure to enter the work effort in an ETC segment. You can also delete a segment.
The ETC Detail section on the resource assignment properties page displays time segments with the start and finish dates and the ETC for each block of work. The work units for consecutive time-varying ETC segments display as one block, for example, 12/7/10 - 12/31/10 90 hours.
When you save your changes, the total ETC for the assignment is recalculated with the sum of all the individual work segments. On the task properties page, the ETC column and the Usage column for the resource reflect the changes you made.
Example
Enter the following time segments and work units:
Time Segment |
Work Units |
---|---|
11/01/11 |
32 |
11/08/11 |
28 |
11/15/11 |
0 |
11/22/11 |
32 |
They appear as:
Time Segment |
Work Units |
---|---|
11/01/11 |
60 |
11/22/11 |
32 |
Follow these steps:
The list page appears.
The task assignments page appears.
The assignment properties page appears.
The resource assignment properties page appears.
Specifies the loading pattern to distribute the ETC for a task assignment over the duration of the task. Autoschedule schedules the work based on this loading pattern.
Values: Back, Uniform, Fixed, Contour, or Front
Default: Front
Select Fixed to enter the distribution of the work effort.
Specifies the start date for the time segment. Click the calendar icon and select a start date for the new time segment.
Specifies the finish date for the time segment. Click the calendar icon and select a start date for the new time segment.
Specifies the number of ETC hours for the time segment.
Copyright © 2013 CA.
All rights reserved.
|
|