Evenly Distribute ETC Over Segments

You can enter a total ETC for a resource assignment. When you enter a total ETC, the ETC for that resource is evenly distributed over all the time segments for the task. When you autoschedule the project, the ETC is distributed between the start and finish dates based on the loading pattern rules.

Follow these steps:

  1. Open the project and click Tasks.

    The list page appears.

  2. Open the Tasks menu and click Assignments.

    The task assignments page appears.

  3. Click the Properties icon next to the name of the desired resource.

    The resource assignment properties page appears.

  4. Complete the following field:
    ETC

    Displays the estimate of remaining hours to complete the task. The estimate is based on the allocation percent for the team staff member between assignment start and finish dates. Also based on the number of hours the resource is available each day.

  5. Save the changes.

More information:

Modify Resource Assignments

About Autoschedule