You can create change requests from existing risks. In addition, the Originating Risk field displays on the change request properties page. This field is a link to the risk from which the change request derived. Basic information, such as the risk name and ID number, are carried over to the new change request for easy setup.
Follow these steps:
Specifies the name of the resource managing the request. The resource is responsible for verifying that the request is managed and tracked appropriately through its lifecycle.
Default: The resource currently logged in
Displays the name of the resource who created the request.
Default: The resource currently logged in
Defines the effect of the change request on the project baseline.
Defines the effect of the change request on other projects.
Describe how this change can benefit the project.
Defines the amount by which the request can change the budget cost of the project. The budget cost is a field defined on the budget properties page.
Defines the number of days by which the request can delay or hasten the overall project schedule.
Defines the number that reflects the request for an increase or decrease in the number of resources needed for the project.
Note: To close the change request, change the status to Closed.