Teams (projects and investments) › Add Resources to Projects by OBS Unit (Investments) › About Team Staff Member OBS Unit
About Team Staff Member OBS Unit
When you add a resource to your project, the default staff OBS unit for the project is the unit used for the resource. The project default staff OBS unit is a field on the scheduling properties page. You can define the resource staff OBS type using the Staff OBS Unit field on the staff member properties page.
The following rules are used when adding resources to projects:
- If the defined resource and project OBS units are the same, then the resource OBS unit is set to that of the project. The value does not change even if the resource properties for the defined resource have a different value.
- If the defined resource and the project OBS units vary, then the resource OBS unit is left undefined (blank).
- If the project OBS unit is not defined, then the resource OBS unit is left undefined (blank).
- When booking a requisition, the booked resource staff OBS value is set using the same rules as replace.
More information:
Add Resources to Projects by OBS Unit (Investments)
Edit Team Staff Member Properties