Previous Topic: Shift and Scale Resource AllocationsNext Topic: About Editing Allocations


Change Resource Default Allocation (Investments)

Use the following procedure to indicate any deviations from the Default % Allocation field. You can unbook a hard-booked resource or extend a resource to do additional project planning.

Follow these steps:

  1. Open the project and click Team.

    The project team staff page appears.

  2. Click the Properties icon for the resource to change allocation.

    The staff member properties page appears.

  3. Complete the following field in the General section:
    Default % Allocation

    Defines the percentage of time you want to allocate the resource to this project (you can enter 0 percent). This amount is reflected in the Allocation and Allocation % columns on the project team staff page.

    Default: 100 percent

    Required: No

  4. Create one row for each deviation from the default allocation in the Planned Allocation and Hard Allocation sections. To create a planned or hard allocation period, complete the following fields in the row:
    Start

    Defines the start date for the allocation period.

    Finish

    Defines the finish date for the allocation period.

    % Allocation

    Defines the expected percentage of time for the resource to work (as tentative or committed) on the investment.

  5. Save the changes.

More information:

About Editing Allocations

Shift and Scale Resource Allocations

Allocations