Previous Topic: Create Execution ConditionsNext Topic: Apply ETC from Task Estimating Rules


Compare Generated ETC with Current ETC

Use this procedure to compare the ETC generated by the task estimating rule with the current ETC (the one in place before running the rules).

Follow these steps:

  1. Open the project and click Tasks.

    The list page appears.

  2. Open the task and click Estimating.

    The task estimating properties page appears.

  3. Select the rule and click Run.

    The run estimating rules page appears.

  4. View the following fields:
    Current ETC

    Displays the total Estimate To Complete (ETC) for the task. The value for this field is derived from the ETC field on the task estimating properties page.

    ETC from Rules

    Displays the total Estimate To Complete (ETC) for the task generated from the applied task estimating rule.