Previous Topic: Cost and Usage Data from Baselines (Service)Next Topic: Set the current Baseline (Service)


Update Baselines at the Service Level

You can update an existing baseline rather than create a new one. For example, update an existing baseline to include data from recently posted actuals. Updating a baseline changes its values accordingly.

Follow these steps:

  1. Open the service.

    The properties page appears.

  2. Open the Properties menu, and click Baseline.

    The service baseline page appears.

  3. Select the check box next to the baseline.
  4. Click Update Baseline.

    The confirmation page appears.

  5. Click Yes.