This section contains the following topics:
View Summary Level Planning Packages (SLPP) Remaining Budget
How to Draw Down SLPP Budget into Work Packages
Delete Summary Level Planning Packages (SLPP)
Create SLPPs using the CWBS element summary planning packages list page. Create them at the lowest level of the CWBS hierarchy at which is the control account. This helps for future work and you draw down the SLPP budget into a control account work package.
Follow these steps:
The properties page appears.
The contract WBS page appears.
The properties page appears.
The list page appears.
The create page appears.
Required. Defines the SLPP name.
Required. Defines the SLPP unique identifier.
Defines the SLPP assigned budgeted amount. When you take a contract baseline, the value is used for the SLPP Budget At Completion (BAC).
Defines the SLPP description.
Required. Defines the SLPP start date.
Required. Defines the SLPP finish date.
Defines the SLPP OBS Unit. This value is used for aggregation of earned value metrics and baseline data on the CPR Format 2 report.
The SLPP is created and displays on the CWBS element summary planning packages list page.
You can view the SLPP remaining budget on the properties page of summary planning package.
When an SLPP balance goes down to zero, the SLPP has no remaining budget. The summary planning package list page displays SLPPs having a budget greater than zero. To view all SLPPs, set the Has Remaining Budget filter field to All and filter the list.
For more information, see the Basics User Guide.
Follow these steps:
The properties page appears.
The contract WBS page appears.
The properties page appears.
The list page appears.
The properties page appears, displaying the remaining budget (BAC) in the Budget field.
You can draw a budget down from your SLPP into a control account work package. Draw the budget for the future work but before you start the work.
Drawing down the budget is not an automated process. You require to draw manually a portion of it, or the entire amount of the SLPP budget down to the work package. Use the following process to draw down your SLPPs and transfer the budget into a planning work package:
You can manually enter the budget amount for the planning work packages that are being drawn from the summary level planning package (SLPP). Enter the budget amount on the properties page of work packages.
Follow these steps:
The properties page appears.
The WBS contract page appears.
The properties page appears.
The control accounts page of CWBS element appears.
The properties page appears.
The list page appears.
The properties page appears.
Specify the budget amount to be drawn from the SLPP into the work package. Then, manually reduce the SLPP budget by the amount you entered in the work package. Use the Budget field on the properties page of summary planning package to report the amount.
Follow these steps:
The properties page appears.
The WBS contract page appears.
The properties page appears.
The list page appears.
The properties page appears.
The SLPP budget is reduced by the amount you are drawing down.
A summary level planning packages (SLPP) converted into a work package can be deleted. You require the Contract - Edit access right to delete SLPPs. You cannot delete SLPPs that have a baseline, even if the current balance is zero.
Follow these steps:
The properties page appears.
The contract WBS page appears.
The properties page appears.
The list page appears.
The confirmation page appears.
|