How to Manage Your Assignments

As an application user, you use the product to manage your assignments. You can view, and update tasks and action items to keep your assignments status up-to-date.

A personal task is a work item for which you can log work in your timesheet and can track the progress.

An action item is a nontask that you assign to yourself, or others assign to you. An action item is an assignment that lets you select an option depending on the status of the work. You can use action items to track the progress of projects and to help ensure that a project is complete and on time.

A process is a series of actions (steps) in resulting in an end. Each step performs a single action that is intended to move the process toward its completion. The completeness of a process instance depends on the status of the steps it contains. When the Finish step is completed, the process instance ends.

You can access your assignments from Overview or Organizer page. The Overview page is the default home page that contains configurable portlets with your action items, notifications, links. The Organizer page contains detailed information about your action items, tasks, processes, and notifications.

Note: For information about how to configure portlets, see the Personalizing CA Clarity PPM User Guide.

Prerequisites:

The following process describes how an application user manages their assignments:

How to Manage Your Information Diagram

To manage your assignments, follow these steps:

  1. Edit an Action Item.
  2. Create an Action Item.
  3. Edit a Task.
  4. View an Initiated or Available Process.

Edit an Action Item

You are the owner of action items you create. As the owner, you can modify or delete an action item. You can modify the properties of a personal action item you create.

Note: For an action item assigned to you by another user, you can update only the status.

Follow these steps:

  1. Open Home, and from Personal, click Organizer.
  2. To update the status of an action item, select the status of the action item and Save.
  3. Click the name of the action item.
  4. Click Edit.
  5. Edit the action item fields, and save.

    The changes to the action item are saved.

Create an Action Item

You can create both personal and project-related action items.

Note: For more information about project-related Management, see the Project Management User Guide.

Follow these steps:

  1. Open Home, and from Personal, click Organizer.
  2. Click New.
  3. In the General section, complete the following fields:
    Subject

    Defines the name for this action item.

    Description

    Defines the description of the action item.

    Priority

    Specifies the priority level of the action item.

    Values: Low, Medium, or High

    Due Date

    Defines the date the action item is due for completion. If desired, select the hour and minute the action item is due.

    Recurring

    Indicates if the action item occurs at regular intervals. If the action item is to occur only once, clear this check box.

    Frequency

    Specifies how often the action item to reoccur.

    Example: Enter 1 in this field to create a status report each week.

    Units

    Specifies the time period during which the action item reoccurs.

    Values: Days, Weeks, Months, and Years

    Until

    Indicate the last date on which you want the action item to reoccur.

  4. In the Notify section, complete the following fields:
    Notify Assignees

    Indicates if a notification is sent.

    Send Reminder

    Indicates if a reminder email notification is sent to the assigned resource (or resources) when the action item is due.

    Time Before Reminder

    Defines the amount of time before an item is due that the reminder occurs. For example, enter 15 in this field, and select Minutes in the Units field.

    Units

    If the Send Reminder check box is selected, this field specifies the unit of time for the reminder.

  5. In the Assignees section, enter the name of the resource to assign the action item and save.
    Assign To

    Defines the name of the resource assigned to the action item.

    Default: The resource currently logged in.

More Information:

Favorites

Getting Started

How to Manage Your Assignments

Edit a Task

You can update a personal or assigned task to ensure that information about tasks is up-to-date.

Follow these steps:

  1. Open Home, and from Personal, click Organizer.

    The action items list appears.

  2. Click Tasks.

    The tasks list appears.

  3. Click on a task that you want to update.

    The following task properties appear. You can edit the appropriate fields as needed:

    Task

    Defines the name of the task. The value for the field is derived from the Name field on the task properties page. On list pages or in portlets, displays the name of the task. You can click the task name to open the task properties page.

    Limits: 64 characters

    Required: Yes

    Investment

    Displays the name for the investment. The value for this field is based on the Project Name field on the project properties page. Click this link to open the investment.

    Start

    Defines the date of starting the task assignment for a resource. The list pages or portlets display the start date.

    Default: Task start date

    Required: Yes

    Note: Define the assignment to start on or after the task start date. If an assignment has actuals, the field is view only.

    Finish

    Defines the date of completing the task assignment for a resource. The list pages or portlets display the completion date.

    Default: Task completion date

    Required: Yes

    Note: Define the assignment to finish on or before the task completion date.

    Actuals

    Defines the total work units that a resource has worked and posted to the task assignment.

    Pending Actuals

    Displays the number of hours entered by a resource on a submitted timesheet that is waiting to be posted.

    ETC

    Displays the estimated hours to complete the task. You can click in the cell to edit.

    Assignment Status

    Displays the status of the task. The value for this field is from the Status field on the task properties page.

    Values:

    • Not Started. No time is posted against the task.
    • Started. Automatically changes the status to "Started" when time was posted against the task.
    • Completed. Automatically changes the status to "Completed" when the task ETC has zero hours and the task status is updated to "Completed".
  4. Click Save.

    Your updates are saved.

View an Initiated or Available Process

You can filter and view a list of initiated or available processes. From a list, you can do the following:

Note: To view a list of all available global processes, process administrator access is required.

Follow these steps:

  1. Open Home, and from Personal, click Organizer.
  2. Click Processes.
  3. Expand the Processes menu, and click Available or Initiated.

    A list page with initiated or available processes appears.

More Information:

Edit an Action Item

Create an Action Item

Edit a Task

Notifications

A notification can be an alert, an email, or an SMS message that notifies you of new activities or changes in CA Clarity PPM. The alerts that you can see are for your assigned action items or overdue timesheets.

Alert notifications appear in the following locations:

More information:

Open an Action Item from Notifications

Open an Action Item from Notifications

The following procedure explains how to open an action item from the notification list. You can delete notifications that you no longer need.

Follow these steps:

  1. Open Home, and from Personal, click Organizer.

    The action items page appears.

  2. Click Notifications.

    The notifications list appears,

  3. Click the link in Message column or the Properties icon that displays next to the alert notification.