Edit Baselines

Use the Multiple Baselines dialog box to edit a baseline's name, description, and code, and to set a baseline as the current baseline.

To edit a baseline

  1. Select Manage from the Baselines group in the Project ribbon.

    The Multiple Baselines dialog box opens.

  2. To set a baseline as the current baseline, select the Current check box next to the baseline you want to set as the current baseline.

    Note: You can select one baseline as the current version.

  3. Click OK.

    The Baseline dialog box closes.

More information:

Set Baselines

Delete Baselines

Rebaseline Projects