Use the Set Baseline dialog box to re-baseline your project. When you rebaseline your project, the current baseline is replaced with the new baseline data.
Note: When you choose to rebaseline the view or selected tasks, the project baseline values are not updated.
You must select all levels of the WBS to rebaseline your project, view, or selected tasks. When you rebaseline tasks that have changed—such as changes to a resource's ETC—the data is not rolled up to the summary task level. Data, however, is rolled down to a phase's tasks when you re-baseline at the summary task level.
When this is the case, you are asked to .
To rebaseline a project
The Baseline dialog box opens.
The current baseline is replaced with the new baseline data.