Review the Prerequisites

Before you use the Kanban Board to manage the product backlog, verify that the following items are set up in CA Clarity Agile and CA Clarity Requirements.

For example, Michael creates a Kanban Board. He identifies the backlog of user stories for the release and prioritizes them in the order of business importance. The following status lanes and WIP limits is configured on the Kanban Board.

Status Lane

Description

WIP Limit

Planned

User stories ready for development.

5

Development

User stories under development.

3

Test

Developed user stories under testing.

2

Completed

User stories ready to close.

5