Field and Value Mapping

The following table shows how sprint, user story, and task information from CA Clarity Agile is used to populate the CA Clarity PPM work breakdown structure fields and values:

CA Clarity Agile Field/Value

CA Clarity PPM Field/Value

  • Sprint Name
  • Kanban Board Name
  • User Story Title
  • Task Title

Task

Assignee

Assignments

Estimated Hours

ETC (only populated in CA Clarity PPM if there is an assignee for the task).

Planned (task status)

Not Started (task status)

In Progress (task status)

Started (task status)

Closed (task status)

Completed (task status)

Sprint start/end date

Task start/end date (if task is assigned to a sprint).

Release start/end date

Task start/end date (if task is not assigned to a sprint).