Task Worklog Mapping

When you enter the hours worked on a task in CA Clarity Agile using the Task Worklog or the Virtual Wall, the following updates occur in CA Clarity PPM:

The following table shows how CA Clarity Agile task worklog information maps to CA Clarity PPM timesheets:

CA Clarity Agile Worklog

CA Clarity PPM Timesheet

Agile User Name/Assigned To

Resource Name

Hours Worked

Hours logged for one day

Hours Remaining

ETC

Work Date

A day in the timesheet time period

Task Type

Charge Code

Each time you update your worklog in CA Clarity Agile, the corresponding timesheet is updated in CA Clarity PPM as long as the timesheet is not in submitted status.

You can delete your worklog in CA Clarity Agile even if time has already been populated in a CA Clarity PPM timesheet. If the timesheet is currently not submitted, it is updated based on the latest updates from CA Clarity Agile. If the timesheet is already submitted, create a timesheet adjustment.