Previous Topic: Map CA Clarity Agile Task Types to CA Clarity PPM Charge CodesNext Topic: Update Roles in CA Clarity Agile from CA Clarity PPM


Link CA Clarity PPM Tasks with CA Clarity Agile

You can link multiple tasks to a single requirement, and you can link multiple requirements to a single task.

Follow these steps:

  1. In CA Clarity PPM, open the linked project.

    The project properties appear.

  2. Click the Tasks tab and click Gantt.
  3. Locate the task and click the icon in the Mapped Requirements column.

    The Mapped Task: Properties page appears with the Requirement and Task Mapping List option selected in the content menu.

  4. Click New.

    The Create Agile Requirement and Task Mapping page appears.

  5. Click the Browse icon and select a CA Clarity Agile requirement to map to the task.
  6. Click Save and Return.

    The Mapped Task: Properties page appears with the requirement listed.

    Note: After the requirement is added to the task, populate the requirement list with the CA Clarity Agile requirement information. If the list is empty, refresh the page.

  7. Choose one of the following options:

    CA Clarity Agile is updated with the information about linked tasks and requirements the next time the Agile Requirement and Task Mapping Sync job runs.

    Note: The sync job does not synchronize the requirement version number and the version status from CA Clarity Agile to CA Clarity PPM.