Previous Topic: Restore a Resource or Resource GroupNext Topic: Show Differences between Resources


Change a Committed Resource or Resource Group Date

You can change the resource's or resource group's date after it is committed. The new date must be between the previous change date and the next change date.

Performing a change date action causes an immediate recalculation.

To change a committed resource or resource group date

  1. In the Resources page, click next to the resource or resource group name and select Change date.

    A confirmation dialog box opens.

  2. Click Yes.

    The Change Resource Date page opens.

  3. In From Date, select a date and time from the drop-down list that you want to change.
  4. In Date, click Open Calendar and select a new date.
  5. Click Change date.