When an Application is generated, a job's run frequency determines whether the job is selected to run in that generation. To specify when the job runs, you can specify an early submission time when you define the job. The server delays the submission of a job until the submission time you specify. You can delay the job submission to let an Application span many days or weeks.
Note: You cannot specify a time in the run frequency of a job.
If you specify a time (such as 9PM), the server delays submission of the job until the next occurrence of that time. If you do not want to submit the job for the next occurrence of that time, specify a date (such as 9PM JULY 25). The job may still wait for predecessor and resource dependencies, if applicable.
You can also delay the submission of a job for a number of minutes after it is eligible to run. For example, you can specify that the server delay submission of a job for five minutes after it becomes ready for submission.
|
Copyright © 2014 CA Technologies.
All rights reserved.
|
|